Luton-10
Thread Starter
Join Date: Jul 2016
Location: Between the check-in desks
Posts: 397
Received 0 Likes
on
0 Posts
As for the issues? I am not going to disclose them, as this was the first trial but the second trial has been cancelled.
Ticket machines don't work so were all switched off with trialists issued with fake tickets.
The Dart trains were not being properly monitored with passengers ending up where they started as they didn't get off the train quick enough.
A passenger got his shoe trapped in the door that couldn't be forced open. Another passenger having a wheel ripped off his suitcase while a third passenger got the extended handle of his suitcase trapped in the door. After a long fight someone on the train who should have got off pulled the case back into the train and off the train went.
The trial was to identity issues and they went away with a long list. I think the next trial has been suspended for H&S reasons. Not properly tested and rushed comes to mind.
Join Date: Jul 2002
Location: In the sticks
Posts: 9,159
Likes: 0
Received 0 Likes
on
0 Posts
LTNman - you mention there will be no road access to the DART as it will be barrier controlled.
Will it still be possible to enter/exit between the railway station and Kimpton Road (yes, by the hotel) without paying for the DART ? I rather like being able to save the money and walk between the airport and train station
Will it still be possible to enter/exit between the railway station and Kimpton Road (yes, by the hotel) without paying for the DART ? I rather like being able to save the money and walk between the airport and train station
The ground floor Dart entrance is open access to both Thameslink and the Dart with just a Thameslink gate line to platform 1. Passengers heading for platform 2 to 4 can either use the platform 1 entrance and follow the existing route to the other platforms or use the escalators and lifts to the first floor, which is also open access. From there passengers either pass through the barriers to the Dart or at the rear of the Dart station, another set of barriers to the railway lines. The second photo shows both sets of barriers.
Last edited by LTNman; 3rd Feb 2023 at 11:43.
Join Date: Jan 2006
Location: Luton
Age: 46
Posts: 125
Likes: 0
Received 0 Likes
on
0 Posts
I'm hoping to be able to access DART from the parkway train station side (arriving on foot) with only a DART ticket, but that will require going through entry and exit Thameslink gate lines. I wonder if I can use a contactless card which won't get charged if it registers me entering and leaving the Thameslink zone within just a few mins?
Join Date: Jul 2002
Location: In the sticks
Posts: 9,159
Likes: 0
Received 0 Likes
on
0 Posts
Good question and lots of unknowns. I can’t see why not as you should be able to buy a through ticket from any U.K. station so why not from the other side of the tracks at Parkway, as Central station is a valid destination. It would mean passing through 3 sets of barriers to board the Dart.
Another more intriguing question is if someone buys a ticket from Central to Parkway and wants to be picked up. As there is no pick up area on the Dart side it would mean crossing the railway tracks into Thameslink territory. I can’t see how a Dart ticket to Parkway would allow access through the Thameslink barriers unless Parkway Thameslink was a separate destination.
Looking at the Thameslink website I can still buy a return ticket to the airport for £3.80 for April 22nd, which is well after the planned opening date of Easter and somewhat cheaper than the £9.80 new fare. Would that ticket still be valid on the Dart?
For Luton residents, Dart tickets will be half price, if booked in advance. A bargain seeing it has already cost them £300m
Another more intriguing question is if someone buys a ticket from Central to Parkway and wants to be picked up. As there is no pick up area on the Dart side it would mean crossing the railway tracks into Thameslink territory. I can’t see how a Dart ticket to Parkway would allow access through the Thameslink barriers unless Parkway Thameslink was a separate destination.
Looking at the Thameslink website I can still buy a return ticket to the airport for £3.80 for April 22nd, which is well after the planned opening date of Easter and somewhat cheaper than the £9.80 new fare. Would that ticket still be valid on the Dart?
For Luton residents, Dart tickets will be half price, if booked in advance. A bargain seeing it has already cost them £300m

Last edited by LTNman; 4th Feb 2023 at 04:45.
Join Date: Aug 2005
Location: LUTON
Posts: 55
Likes: 0
Received 0 Likes
on
0 Posts
Good comments on fares.
One thing I could suggest is there is a national fares rise on 1 March. It is normal at the same time to alter availability and conditions of general tickets (i.e. not those special offers from TOC). It is possible the new fares tables from 01/03/23 may contain conditions changes ?
Re. access across Parkway station from the Up side (Kimpton Road) to Down side (Gypsy Lane) it would be unusual to say the least to allow cross station access. There are a very limited number of GB stations where this is possible already BUT all of them have some historic public right of way embedded into them (e.g. including but not limited to Stockport, Guildford, Sheffield) that requires access through ticket gates and use subway / foorbridge. Stockport they give you a bit of card and manually open the gates (or did pre covid not been there since) the others I'm not sure what they do.
I can't think of any station where the provision of any new facility - including any transport interchange - on one side has been provided with customer access from the opposite.
I remember there was a huge debate in rail anorak circles with the rebuilt Thameslink Blackfriars that spans the Thames with new additional entrances on the south bank. There were a lot of people getting hot under the collar demanding it as a free walking route along the platforms, that, apart from sightseeing, was based on accessing LU District line from the south bank. Unless one has reached the daily Oyster fare cap, touch in one end touch out the other does create a journey / fare / penalty.
I am not saying it can't be done. Far from it. It is very easy to implement. I'm just saying I can't think of an example where this is allowed anywhere except historic rights of ways embedded in laws/byelaws.
OK total digression but examples. Interesting to see how Luton Parkway does all this.
PS don't affect me; I have a Luton to London annual season ticket; should I wish to cross Parkway I simply enter and exit with the season.
One thing I could suggest is there is a national fares rise on 1 March. It is normal at the same time to alter availability and conditions of general tickets (i.e. not those special offers from TOC). It is possible the new fares tables from 01/03/23 may contain conditions changes ?
Re. access across Parkway station from the Up side (Kimpton Road) to Down side (Gypsy Lane) it would be unusual to say the least to allow cross station access. There are a very limited number of GB stations where this is possible already BUT all of them have some historic public right of way embedded into them (e.g. including but not limited to Stockport, Guildford, Sheffield) that requires access through ticket gates and use subway / foorbridge. Stockport they give you a bit of card and manually open the gates (or did pre covid not been there since) the others I'm not sure what they do.
I can't think of any station where the provision of any new facility - including any transport interchange - on one side has been provided with customer access from the opposite.
I remember there was a huge debate in rail anorak circles with the rebuilt Thameslink Blackfriars that spans the Thames with new additional entrances on the south bank. There were a lot of people getting hot under the collar demanding it as a free walking route along the platforms, that, apart from sightseeing, was based on accessing LU District line from the south bank. Unless one has reached the daily Oyster fare cap, touch in one end touch out the other does create a journey / fare / penalty.
I am not saying it can't be done. Far from it. It is very easy to implement. I'm just saying I can't think of an example where this is allowed anywhere except historic rights of ways embedded in laws/byelaws.
OK total digression but examples. Interesting to see how Luton Parkway does all this.
PS don't affect me; I have a Luton to London annual season ticket; should I wish to cross Parkway I simply enter and exit with the season.
Join Date: Jun 2009
Location: Bedford, UK
Age: 69
Posts: 1,319
Likes: 0
Received 0 Likes
on
0 Posts
DART ? You can vote your opinion here
https://www.bedfordshirelive.co.uk/n...oughts-8102578
https://www.bedfordshirelive.co.uk/n...oughts-8102578
Join Date: Jul 2002
Location: In the sticks
Posts: 9,159
Likes: 0
Received 0 Likes
on
0 Posts
Electrically powered and energy-efficient, once underway the project should encourage more people to leave their cars at home, decreasing carbon emissions by 70 per cent.
Last edited by LTNman; 5th Feb 2023 at 17:37.
Join Date: Nov 2001
Location: London Whipsnade Wildlife Park
Posts: 4,961
Likes: 0
Received 0 Likes
on
0 Posts
Good news for the residents of Luton with the 'Game Changing Debt' of the DART! Independent inquiry coming.
https://www.lutontoday.co.uk/news/tr...rspend-4019705
https://www.lutontoday.co.uk/news/tr...rspend-4019705
Join Date: Jul 2002
Location: In the sticks
Posts: 9,159
Likes: 0
Received 0 Likes
on
0 Posts
What won’t be covered is why did the Council agree for the Dart to be built in the first place when the airport was capped at 18m and there wasn’t even a hint of airport expansion. The Dart is only needed for a 32m airport and that planning application hasn’t even been submitted yet.
Join Date: Jan 2005
Location: Not so many places currently
Age: 59
Posts: 3,008
Likes: 0
Received 0 Likes
on
0 Posts
Oh dear, stands 41 & 41L pushed back 2 weeks and Delta 3 weeks.
EGTT/QMXLC/IV/BO /A /000/999/5152N00022W
A) EGGW
B) 23/02/15 17:17 C) 23/03/02 23:59
E) TWY DELTA CLOSED BETWEEN DELTA 1 AND SOUTH OF FOXTROT 5 DUE WIP
Q) EGTT/QMPLC/IV/BO /A /000/999/5152N00022W
A) EGGW
B) 23/02/15 17:33 C) 23/02/28 18:00
E) STAND 42 AND STAND 42L CLOSED DUE TO WIP.
EGTT/QMXLC/IV/BO /A /000/999/5152N00022W
A) EGGW
B) 23/02/15 17:17 C) 23/03/02 23:59
E) TWY DELTA CLOSED BETWEEN DELTA 1 AND SOUTH OF FOXTROT 5 DUE WIP
Q) EGTT/QMPLC/IV/BO /A /000/999/5152N00022W
A) EGGW
B) 23/02/15 17:33 C) 23/02/28 18:00
E) STAND 42 AND STAND 42L CLOSED DUE TO WIP.
Join Date: Aug 2005
Location: LUTON
Posts: 55
Likes: 0
Received 0 Likes
on
0 Posts
Have there actually been any more DART trials after that first date ?
I have lost track, there /should/ have been 2 since, but per upthread at least the next one following that first one was reported to have been cancelled.
I have lost track, there /should/ have been 2 since, but per upthread at least the next one following that first one was reported to have been cancelled.
Join Date: Jul 2002
Location: In the sticks
Posts: 9,159
Likes: 0
Received 0 Likes
on
0 Posts
Second and fourth trials cancelled and reported as complete. Signage was rubbish. How can they spend 5 year’s building it and still get the signage wrong? This photo from Luton Rising Temperature showing the signage to the drop off area except there isn’t one according to a company spokeswoman.

Join Date: Aug 2005
Location: LUTON
Posts: 55
Likes: 0
Received 0 Likes
on
0 Posts
Second and fourth trials cancelled and reported as complete. Signage was rubbish. How can they spend 5 year’s building it and still get the signage wrong? This photo from Luton Rising Temperature showing the signage to the drop off area except there isn’t one according to a company spokeswoman.


Ta for update on trials
Paxing All Over The World
I expect that the PR blurb of the construction company and their porject manager has lots of things about 'Good communication' and 'Feedback at every level' etcetera.
Join Date: Dec 2020
Location: UK & Estern Europe
Posts: 39
Likes: 0
Received 0 Likes
on
0 Posts
2022 CAA Figures for LTN
CAA Figures for air travel in 2022.
Luton was the fifth busiest airport in the UK in terms of passenger numbers, handling 13.322 million.
Source - CAA
Luton handled 9,244 aircraft movement.
What is interesting here is 2,013 of these were "business aviation" and the total number of "business aviation" flights across all London airports was 2,892, so Luton handled nearly 70% of all these flights!
Source - CAA
Luton was the fifth busiest airport in the UK in terms of passenger numbers, handling 13.322 million.
Source - CAA
Luton handled 9,244 aircraft movement.
What is interesting here is 2,013 of these were "business aviation" and the total number of "business aviation" flights across all London airports was 2,892, so Luton handled nearly 70% of all these flights!
Source - CAA