The central station had a 59 week build schedule and was due to start July next year. On completion the DART equipment was meant to be going in which was meant to take 48 weeks. After that there was 25 weeks of testing and commissioning which took the completion date to April 2021. We will have to see if they can make up the time but without a complete station which contains the maintenance area just beyond it might mean the project is set for a delay.