A part of Signature's new apron has opened.
Work has started today to tarmac a route to the new (temporary?) entrance.
Two sections of the covered walkway arrived on site this week and were joined together. Today two cranes are onsite so maybe it will be lifted into position today?
In the middle half of the photo and to the left of the taxi rank work has started in the former temporary home of the priority drop off and pick up area, which has moved into the short term car park. This area will contain the third core and two support columns for a further 100m section of covered walkway.
Work continues on the link to the pier.