A little more detail of who is doing what, taxiway extensions finished by 2017 starting later this year, just fill in on turns, new entry/exits to 08/26 ???
An error in that report is the 2026 completion date. That has been brought forward to 2020.

Phase 1 to be finished next year.
a. Dualling of the Airport access road
b. Minor changes to the Holiday Inn Roundabout to accommodate the new
road
c. Remodelling of the Central Terminal Area (CTA) and the Drop-Off Zone and
Taxi Rank
d. Remodelling of the junction into the Mid-Term Car Park (MTCP)
e. Construction of the multi-storey car park
f. Construction of the pedestrian bridge link across the CTA to the short term
car park or any agreed alternative
g. Construction of the link building between the old and new terminals
h. Extension of the baggage reclaim area within the terminal
i. Construction of the walkway to Stand 9L/60
j. Infills to Pier A
k. Construction of new Pier B.
l. Extension to 08 taxiway

Phase 2 comprises the construction of Taxiway Foxtrot and the extension to the West Apron. These works are planned to commence in 2017 and be complete by 2019.

Phase 3 will include the extension of the parallel taxiway at the 26 end. Completion 2020.

The above was how it was going to be phased but things could have changed since last February. Worth noting that they need all the soil they can get from the existing upgrade to build the 26 taxiway which might be one of the reasons it is the last job to be done.