Weekly redevelopment update

Signature's new FBO is now taking shape.




The shuttle bus bay to the station is now getting railings so is looking close to opening.


The 2 bays built over the existing pavement of the old bus station are now complete making 11 in total that are finished.


The foundations of the passenger bridge between the short term car park and the multistory car park have been laid this week.


The mid term car park extension is getting the same rubbish gravel and cinders finish for the parking bays as the rest of that car park. That whole car park is a disgrace so it is clear it isn't going to be upgraded like the short term car park.

The photo shows a better section of the existing surface of the car park and the new surface that will soon look like the old surface after a year or two.