The implementation phase is scheduled to be complete on 1st july 2017.


Between 1st Jan 2016 and then there are four things due to happen.

- AW189 (aka The Westland Affair Mk XIII)

- NVG for Stornoway and Sumburgh ... ...

- GAP to MAIN contract changeover at Lee and Sumburgh (1st Apr 2017) then Stornoway (1st Jul 2017)

- End of service at Portland (30th Jun 2017)