Originally Posted by CAP493
No Sir! Until 30th November... However, the drain construction, culvert and cable ducting work could fnish about 7-10 days early, in which case reversion to 24/7 might happen before the end of November.
I was quoting this Class 1 . . .

AGA : Q)EGTT/QMRLC/IV/NBO/A/000/999/5152N00022W005
FROM 06/10/17 10:32 TO 06/10/28 04:45 A2633/06
E)RWY 08/26 CLOSED MON-SAT 2259-0445. RWY WILL OPR WITH FULL CAT 3
AERONAUTICAL GROUND LIGHTING. FULL DETAILS AVBL IN SUP S6/2006.

. . . which I suppose could be meant to be just referiing to the lighting. Supp S6/2006 does state 30 Nov but it ought to be made clear.