AOG costs

Sorry if this is an intrusion

My son works for a company that supplies specialist aluminium castings to the aviation industry among others. As part of one of their contracts they hold a quantity of spares for BAe systems to cover AOG.

He's just asked me for an indication, roughly, of the hourly cost of say a BAe 146 being AOG awaiting parts?

Nothing other than him showing general inerest.
west lakes is offline  
Reply
Old 12th October 2009 | 21:02
  #2 (permalink)  
 
Joined: Nov 2000
Posts: 1,432
Likes: 0
From: Dre's mum's house
Less than flying the heap!
The Real Slim Shady is offline  
Reply
Old 12th October 2009 | 21:10
  #3 (permalink)  
Thread Starter
Cleverly disguised as a responsible adult
 
Joined: May 2007
Posts: 1,117
Likes: 0
From: On the western edge of The Moor
Stop being superior with you B737-800's

(and be glad they don't make bits for them - or else!!)
west lakes is offline  
Reply
Old 12th October 2009 | 21:27
  #4 (permalink)  
Registered User **
 
Joined: Mar 2009
Posts: 480
Likes: 0
From: USA
Differs from operator to operator. If they have no extra lift, they may be responsible for hotel costs, getting the pax on another airline or leasing a aircraft depending on gow long the aircraft is down for. If they keep spare aircraft around, the cost is much less, but then again they are not making money with the spares.
muduckace is offline  
Reply
Old 14th October 2009 | 02:03
  #5 (permalink)  
20 Anniversary
 
Joined: Feb 2005
Posts: 4,581
Likes: 0
From: flyover country USA
Right. If they are in a slack period, thus excess capacity, and the bird isn't AOG in East Podunk, there may be little extra cost over and above mortgage premiums or lease fees.

That can be interesting for the lawyers to sort out.
barit1 is offline  
Reply
Old 14th October 2009 | 02:18
  #6 (permalink)  
 
Joined: Aug 2006
Posts: 61
Likes: 0
From: The Rock
If you have an Aircraft that is planned to operate 6 flights a day and the choice is cancel all 12 flights and take the consequences with your customers.

Or lease in another operator to do the flights.

As you will still pay all the costs fuel handling etc all you need to pay is the wet lease BAe 146 would be £10,000 per day give or take a £1K or three.
Island Jockey is offline  
Reply
Old 15th October 2009 | 20:16
  #7 (permalink)  
20 Anniversary
 
Joined: Sep 2002
Posts: 187
Likes: 2
From: Europe
In a rather complex contractual framework between an airline and an MRO, any day of a planned (!) maintenance layover of an A340 classic was evaluated with approx. 30.000EUR. That means if the MRO could not squeeze an activity into any of the planned groundings (letter checks for instance), but had to ask for a special layover, this sum was on the tables...

Regards, J.V.
jettison valve is offline  
Reply

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off



Contact Us - Archive - Advertising - Cookie Policy - Privacy Statement - Terms of Service

Copyright © 2026 MH Sub I, LLC dba Internet Brands. All rights reserved. Use of this site indicates your consent to the Terms of Use.