Phased or staggered C-Checks

Hi,

I was wondering if anyone had some information on approved programs for phasing or staggering C-checks for a Boeing aircraft. For example is it possible to do a standard C1-check separated by a number of vists for a B737-800? Also what MRO providers are currently operating these programs and for who?

Thanks, Craig
CraigS is offline  
Old 16th Nov 2006, 16:00
  #2 (permalink)  
Cunning Artificer
 
Join Date: Jun 2001
Location: The spiritual home of DeHavilland
Age: 76
Posts: 3,127
Likes: 0
Received 0 Likes on 0 Posts
Your questions cannot be answered simply, Craig. They raise a whole lot more questions, the first being "what regulatory environment? FAA? EASA? Other?"

EASA for example, requires a commercial operator to have a Continuing Airworthiness Management Organization (CAMO) with a "nominated postholder" responsible for managing it. The CAMO must include a person responsible for the quality system, with direct access to the accountable manager (usually the CEO). The operator's quality system is extended to the contracted maintenance organization. The maintenance and quality systems are an AOC responsibility that cannot be delegated, to an MRO or anyone else. This means that although producing the maintenance schedule can be contracted to an MRO, responsibility for its content and the managerial oversight of compliance with it, cannot be delegated.

So...

1. Generally speaking, you can split up check packages pretty much as you please, as long as all maintenance is accomplished within the approved maintenance intervals. The Boeing MPD provides recommendations, but drawing up a maintenance schedule from it and getting the schedule approved is the operator's responsibility. The operating environment determines the actual intervals - e.g high cyle/short sectors or low cycle/long sectors?

2. MROs are commercial businesses and any MRO will run whatever maintenance programme the customer desires. They aren't responsible for producing it - although they will if you pay them cold, hard cash. Responsibility for getting its content approved by the regulator remains with the AOC holder.
Blacksheep is offline  

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off



Contact Us - Archive - Advertising - Cookie Policy - Privacy Statement - Terms of Service

Copyright © 2024 MH Sub I, LLC dba Internet Brands. All rights reserved. Use of this site indicates your consent to the Terms of Use.