Runway Friction Test to Open Runway ... How Long in the hold!
Thread Starter
Join Date: Jan 2008
Location: dublin
Posts: 2
Likes: 0
Received 0 Likes
on
0 Posts
Runway Friction Test to Open Runway ... How Long in the hold!
Scenario : Winter Ops : Airfield closed due to reopen : What is the normal elapsed time from commencement of friction test (at say LHR or LGW) to runway declared open ?.
Join Date: Sep 2003
Location: 59°45'36N 10°27'59E
Posts: 1,032
Likes: 0
Received 0 Likes
on
0 Posts
Cantīs speak for the airfields in question, but at Oslo we aim to have first arrival at 6nm+ final when the friction testers leave the runway. (That is, friction test at completion of sweeping) Most times the sweeping use less time than calculated, so first arrival is often at 10nm when they are done.
Friction testers, 2x that test each side of the centerline, then compare the results at the crew leader reports the estimated friction, contamination etc via R/T to the TWR. (Norway does not report friction coeffcient any more)
The friction testers (driving at 90 km/h) start their run to time their arrival at the runway end at the same time as the sweeper/blower/sanding "train" which does about 40 km/h
Friction testers, 2x that test each side of the centerline, then compare the results at the crew leader reports the estimated friction, contamination etc via R/T to the TWR. (Norway does not report friction coeffcient any more)
The friction testers (driving at 90 km/h) start their run to time their arrival at the runway end at the same time as the sweeper/blower/sanding "train" which does about 40 km/h
Join Date: Feb 2007
Location: EU
Posts: 218
Likes: 0
Received 0 Likes
on
0 Posts
At our airport it takes around 6 minutes for a sweeper team to go in one direction ( 3200m RWY).
As stated above friction testers try to leave together with sweeping team.
But the tricky part is,when you start to vector 1st arrival to be at around 5 nm upon RWY is clear, crew leader says,that friction is still poor and they need another run.
As stated above friction testers try to leave together with sweeping team.
But the tricky part is,when you start to vector 1st arrival to be at around 5 nm upon RWY is clear, crew leader says,that friction is still poor and they need another run.
Join Date: Jan 2004
Location: England
Posts: 764
Likes: 0
Received 0 Likes
on
0 Posts
I think in UK if runway is swept to "blacktop" then friction tests are not carried out prior to re-opening as the runway will be normally be wet with de-icer and friction tests on a wet runway are considered to be unreliable. The friction calibrations are carried out on a dry runway using a self wetting device, so provided the calibration results show figures above acceptable levels then then the wet runway braking action should be fine.
If the runway state report gives ice patches, slush etc then operators should apply their SOPs based on the runway state given at the time. CAA document CAP683 on CAA website details the UK guidelines, also the UK AIP GEN section has some information on this.
If the runway state report gives ice patches, slush etc then operators should apply their SOPs based on the runway state given at the time. CAA document CAP683 on CAA website details the UK guidelines, also the UK AIP GEN section has some information on this.