ATC Issues A place where pilots may enter the 'lions den' that is Air Traffic Control in complete safety and find out the answers to all those obscure topics which you always wanted to know the answer to but were afraid to ask.

ILS approach clearance terminology

Thread Tools
 
Search this Thread
 
Old 20th Aug 2005, 00:52
  #1 (permalink)  
Thread Starter
 
Join Date: Aug 2000
Location: formally Alamo battleground, now the crocodile with palm trees!
Posts: 960
Likes: 0
Received 0 Likes on 0 Posts
Exclamation ILS approach clearance terminology

I stumbled over this during my last recurrent. Let's say that you are getting ready to shoot (as they say in the US) an ILS approach, with the glideslope out of service. What is the correct terminology that should be used by the controller? "Cleared for the ILS 9R, Glideslope OTS", or "Cleared for the LOC 9R"?

It was argued that "Cleared for ILS, (G/S OTS)" should be used in order to avoid confusion with a different procedure. I have never flown to places where an ILS and LOC approach were on different plates (If it would be the case, would the procedure read like LOC-Y Rwy 9R?). Additionally, some controllers tell you to expect the ILS with GS OTS, but they clear you ("cleared for ILS") and omit the GS OTS in the clearance since it has been previously mentioned.

What does the controller handbook say?

7 7 7 7

Last edited by Squawk7777; 20th Aug 2005 at 01:39.
Squawk7777 is offline  
Old 20th Aug 2005, 03:25
  #2 (permalink)  
 
Join Date: Jul 2000
Location: West
Posts: 399
Likes: 0
Received 0 Likes on 0 Posts
From the FAA Instrument Procedures Handbook

http://av-info.faa.gov/terps/IPH/CH%2005a.pdf

"The name of an instrument approach, as published, is
used to identify the approach, even if a component of
the approach aid is inoperative or unreliable. The controller
will use the name of the approach as published,
but must advise the aircraft at the time an approach
clearance is issued that the inoperative or unreliable
approach aid component is unusable. (Example:
“Cleared ILS RWY 4, glide slope unusable.”)"
None is offline  
Old 20th Aug 2005, 08:05
  #3 (permalink)  
 
Join Date: Aug 2002
Location: Up north
Posts: 1,658
Likes: 0
Received 0 Likes on 0 Posts
I find it quite common that ATC clears us to "Intercept LOC RWY xx, report established", once "XXXX established RWY xx" has been called the final clearance is "XXXX you are cleared to descend with the procedure".

/CP
CaptainProp is offline  
Old 20th Aug 2005, 08:37
  #4 (permalink)  
9Ws
 
Join Date: Dec 2004
Location: Here and there
Posts: 95
Likes: 0
Received 0 Likes on 0 Posts
Controller : "Cleared for Localiser-Only approach Rwy.... , report established".

Pilot : "Established Localiser Rwy...."

Controller : "Continue approach Rwy.... , contact Tower (1.. . .. freq.)"
9Ws is offline  

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off



Contact Us - Archive - Advertising - Cookie Policy - Privacy Statement - Terms of Service

Copyright © 2024 MH Sub I, LLC dba Internet Brands. All rights reserved. Use of this site indicates your consent to the Terms of Use.