Is FIFO to this mine very short term?
The village will be developed in three stages. Stage one will see the initial capacity of 250 beds, to be built at the start of construction activities.
Stage two will see the adding of 1000 beds to bring capacity to 1250 beds, which is expected to be needed in the second year of construction with stage three set to add 750 beds to bring the total capacity of the village to 2000 beds by the start of mining operations.
Adani outlined the workers accommodation village would be developed with an elevated sense of community, as a series of accommodation unit clusters to promote a community environment, with each cluster having access to its own recreation and other facilities.
The design philosophy for the workers accommodation village was centred on providing an attractive living environment for the construction and maintenance workers in the
short term while also establishing a framework whereby the settlement can
ultimately be integrated into the permanent workers accommodation village.