TP progress - Stands 213 and 214 reopened today, minus air-bridges for walk-in walk-out use. Stands 215 and 216 now closed for three weeks for similar treatment. Stand 216 was a remote but will become a walk-out. Meanwhile the new gate lounge steelwork is going up at Stand 212. All this is temporary but longer-term i.e. until terminal extension completed in 2020. The Pier 1 construction site now fully closed off as a landside area alongside what remains of Staff West, steelwork to start going up in next few weeks. By the end of the year the skyline around T2 will be a forest of cranes.