Originally Posted by
Bagso
The third busiest station on the underground network handling 52 million passengers a year. Adding a fourth platform, to an underground station whilst keeping all four lines operational is a phenomenally complex operation. Complex = costly. By contrast the work at MAN is relatively simple. Also, to be clear the billion £ price tag is misleading as only £600m of it is actually construction cost.