BAE kicks off major nuclear submarine yard upgrade

BAE kicks off major nuclear submarine yard upgrade

LONDON — An eight-year redevelopment scheme enabling BAE Systems nuclear submarine facility to build a new generation of nuclear missile boats for the Royal Navy has got underway in northwest England. The rebuilding program at the Barrow-in-Furness, Cumbria, nuclear submarine yard has started with the construction of a £23 million ($36.1 million) logistics facility, BAE announced Aug 20.

Subject to parliamentary approval, the Conservative government is expected to decide next year to give the final go ahead to the Successor program aimed at replacing the four Trident missile equipped, Vanguard-class submarines, which have provided Britain's nuclear deterrent capability since 1995. The government is committed to build four Successor submarines, with steel for the first boat being cut at the BAE yard in 2016 and an inservice date of 2028.

To equip the yard for construction of the largest submarines it has ever built, between £300 and £400 million is being spent expanding and upgrading the yard. In it's 2014 update to Parliament on progress in the future nuclear deterrent, the overnment outlined its part in financing the facilities upgrade program.

The report said the Ministry of Defence had brought forward, or reprofiled, £261 million of funding into the current assessment phase offering better value for money investing in facilities at the yard. The reprofiling also allowed for long lead item ordering. "The MoD is able to re-pay the company for the cost of the facilities as building work progresses, rather than recovering the costs across the build programme as a whole. This approach is expected to reduce the cost by some £42 million from that originally planned," said the report.

BAE said the work will include a "mixture of new build projects and the refurbishment of existing facilities in what is the most significant redevelopment of the site since the 1980s." The company wouldn't provide details of the redevelopment but previous reports list a new quayside, extension of the Devonshire Dock Hall building, two new pressure hull unit facilities and refurbishing the main fabrication facility as being among the projects alongside the new logistics center. At nearly 300 meters long and over 50 meters high, the Devonshire Dock Hall where BAE assembles the submarines is already one of the largest buildings in northern England. .

Allan Day, the director of the redevelopment program at BAE Submarines, said "the infrastructure this redevelopment will provide, together with our highly skilled workforce, will be critical in delivering these submarines to the Royal Navy."

The improvement to facilities in support of the Successor program is not limited to BAE. Nuclear propulsion unit supplier Rolls-Royce is updating and refurbishing it's aging factory at Raynesway, Derby, to build the new PWR3 power plant.........