Nope USN funded...

Exhibit R-2A, RDT&E Project Justification: PB 2015 Navy
Date: March 2014

Appropriation/Budget Activity 1319/5
R-1 Program Element (Number/Name) PE 0604329N / Small Diameter Bomb (SDB)
Project (Number/Name): 3072 / Small Diameter Bomb (SDB)

B. Accomplishments/Planned Programs ($ in Millions, Article Quantities in Each)
FY 2013
FY 2014
FY 2015

Continue support of EMD and integration of SDB II with F-35B and F-35C.

Continue support of SDB II prime contractor and government support of weapon development efforts. Begin specific F-35B and F-35C efforts with SDB II prime contractor which were delayed to FY15 to accommodate the JSF OFP change from Block 3 to Block 4..........

FY 2015 Plans:

Continue F-35 UAI OFP development and coding and support fit checks and testing with SDB II Weapon vendor. Begin F-35 bay modifications required for SDB II/JSF/JMM BRU integration. Full manning of JSF prime contractor team to support SDB II weapon development and integration......

D. Acquisition Strategy

The SDB Increment II acquisition strategy is to conduct a full and open competition to select up to two contractors to compete during a planned 42-month risk reduction phase prior to entering EMD. This competition began April 17, 2006 with the signature of contracts to the competing contractors: 1) Raytheon and 2) the team of Boeing and Lockheed Martin.

A Fixed Price Incentive Firm Target type contract for EMD, including Firm Fixed Price procurement options for Lots 1-3 was awarded to Raytheon August 9, 2010. Lots 4 & 5 are included in the contract, but are Not-To-Exceed options.

The Navy funding will support Navy-unique efforts for SDB Increment II, such as aircraft integration, ship suitability, studies and analysis, and program management and government in-house support. These efforts will be performed on several cost-type contracts or through cost reimbursable work requests to government activities and contractors.........

Selected Acquisition Report (SAR) - Small Diameter Bomb Increment II (SDB II) As of December 31, 2012

........The SDB II program office has made considerable progress on the F-35 risk reduction effort to address the ongoing F-35 System Development and Demonstration program delays. The SDB II team successfully conducted F-35B and F-35C weapon’s bay fit checks utilizing production jets. The data collected during these fit checks will be used to finalize the modification of the F-35B weapon's bay. These efforts are on track and serve as a critical risk reduction event for both the SDB II and F-35 programs.

Program Background:

A $450.8 million Fixed Price Incentive Firm-type Engineering and Manufacturing Development contract was awarded to RMS, Tucson, Arizona on August 9, 2010. RMS will complete the design, development, weapon integration, and test for the joint interest SDB II program. F-15E integration is being accomplished by Boeing (St. Louis, Missouri) through the F-15 Development Systems Program Office using Air Force SDB II funding. The F-35B and F-35C aircraft integration contract will be awarded to Lockheed Martin (Fort Worth, Texas) by the F-35 Joint Strike Fighter Joint Program Office using DoN SDB II funding......