If a 3 phase TDP was completed in 1996, why does the convening authority say the CWS issue only began in 1998? Am I correct in saying this is exactly what Hadden-Cave did, saying nothing was wrong before 1998 despite evidence to the contrary?
Simple answer is that neither he nor the SI team reviewed the pre-1998 documentation.
DV