This was an interesting quote indeed.....
Originally Posted by Spaszinbad
DR. J. MICHAEL GILMORE, DIRECTOR, OPERATIONAL TEST AND EVALUATION, OFFICE OF THE SECRETARY OF DEFENSE; BEFORE THE SENATE APPROPRIATIONS COMMITTEE SUBCOMMITTEE ON DEFENSE 19 Jun 2013
"...The program has also dedicated 42 flights to investigating deficiencies in the helmet mounted display system. Seven aircraft from all three variants flew test missions from October 2012 through May 2013 to investigate jitter in the helmet mounted display system, night vision camera acuity, latency in the Distributed Aperture System projection, and light leakage onto the helmet display under low-light conditions. Although some progress has been achieved, results of these tests have been mixed according to comments from the test pilots. Testing could not be completed within the full operational flight envelope evaluating mission-related tasks, as the full combat flight envelope has not been released. Filters for reducing the effects of jitter have been helpful, but have introduced instability, or “swimming,” of the projected symbology. Night vision acuity was assessed as not acceptable with the current night vision camera, but may be improved with the ISIE-11 camera under consideration by the program. Latency with the Distributed Aperture System projection has improved from earlier versions of software, but has not yet been tested in operationally representative scenarios. Light leakage onto the helmet display may be addressed with fine-tuning adjustments of the symbology brightness - a process pilots will have to accomplish as ambient and background levels of light change. Although not an objective of the dedicated testing, alignment and “double vision” problems have also been identified by pilots and were noted in my report earlier this year on the F-35A Ready for Training Operational Utility Evaluation (OUE). Whether the progress achieved in resolving the problems discussed immediately above has been adequate will likely not be known with confidence until the Block 2B operational evaluation is conducted in 2015...."
_____________________________
....but he also said some other very interesting things,...
F35 program may be unaffordable, auditor says | The Center for Public Integrity
Originally Posted by J. MICHAEL GILMORE before the panel
the Pentagon’s chief weapons tester, warned that the fighter’s costs are climbing – not shrinking as they typically do once production begins -- as officials scramble to fix problems cropping up during flight tests of planes already delivered by the manufacturer, Lockheed Martin Corp. The “most challenging portions” of the testing have not yet begun, he said.

“We haven’t actually tested any combat capability,” Gilmore told senators, adding that there may not be enough time or money for full testing of these crucial capabilities in 2018, as scheduled.

Gilmore warned that F-35 may suffer further delays due to the budget sequester. “Reduced funding for test resources and infrastructure while the F-35 is under development . . . will likely add to the pressure to either extend [the design and development phase] or accept reductions in capability,” he said.

He blamed the high cost of making design and production changes on “concurrency,” the practice of buying planes even as they are undergoing testing. “Production in this program started before there was any flight testing at all, which was unprecedented in the history of aircraft development programs,” Gilmore said. “That’s about as concurrent as you can get – that’s pretty much 100 percent concurrency. Obviously that’s a bad thing.

“We need to have more rigorous developmental testing. We need to let that testing proceed before we make production decisions,” he added.
....and finally to support LowObservable's assessment.
Durbin asked “if any alternative is being considered for a less costly fighter.” He was told the country could not afford to start from scratch.

“I don’t believe we have any alternative but to make the program work,” Gilmore said.
kbrockman is offline