Guernsey Airport rebuild
The declared distance will remain at 4800ft but is being shifted to west to acommodate RESAs - as you suggest. The dip at the western end has been filled in and all aprons and taxiways wil be reconstructed. Project is just at its half-way point, currently running 5 weeks late due to weather/rain - but this is expected to be made up - completion next spring.
Good article describing work in today's Guernsey Evening Press.