"The transcribed CVR indicates that standard ECAM discipline was not accomplished. Without announcement or communication to the PNF, a sustained pitch-up occurred, even as the PNF attempted to do the ECAM drills. There was no announcement of the ECAM messages from the PF, and their subsequent response was done in an undisciplined, halting manner that did not initiate and did not complete as per SOPs*. There was no evidence of CRM."

You are missing the evidence to support your conclusion. The CVR is not complete, we do not know what is missing....

Speculation, over time, morphs into gospel...

As expected, BEA succeeds.