PPRuNe Forums - View Single Post - Canada: Cormorant & Cyclone thread
View Single Post
Old 6th Jul 2012, 13:57
  #136 (permalink)  
SansAnhedral
 
Join Date: Nov 2010
Location: Earth
Posts: 699
Received 15 Likes on 10 Posts
Cyclones touch down in Shearwater | Vertical - Helicopter News

CYCLONES TOUCH DOWN IN SHEARWATER
Friday July 6th 2012 - by Ken Pole


At the end of June, the Royal Canadian Air Force took delivery of two long-awaited Sikorsky CH-148 Cyclones at 12 Wing Shearwater, N.S. However, neither is the aircraft that has been the subject of controversy since it was delivered to the base early last year.

That original model, Maritime Helicopter 806, has been returned to the Sikorsky assembly centre in West Palm Beach, Fla., for unspecified modifications. It will be returned to Shearwater “at a later date,” said the Department of National Defence (DND).

The newly-arrived pair of Cyclones, MH805 and 808, which remain Sikorsky’s property until the DND takes possession, are still considered “interim maritime helicopters” and, like 806, are being used primarily for maintenance and non-flight aircrew training.

“Some critical work remains outstanding before the Canadian Forces [CF] can take formal delivery of the first interim maritime helicopters,” DND commented. “Most notably, a Canadian military flight clearance and training for the initial cadre of aircrew and technicians need to be completed. . . . Once the delivery requirements have been met, DND/CF will take delivery . . . to commence initial operational test and evaluation.”

While official lips are sealed at DND and Public Works & Government Services Canada (PWGSC), the other department most involved in the procurement, the fundamental deficiency is understood to be the power-to-weight ratio. The original General Electric CT7-8A1 evidently was heavier than expected which, coupled with “Canadianization” of what was supposed to be an off the shelf (OTS) aircraft, compromised its performance.

The OTS angle was highlighted by the Office of the Auditor-General, which said in a report to Parliament in late 2010 that DND not only had failed to adequately assess the “developmental nature” of the aircraft, but also had underestimated “the risks related to cost and the complexity of the required technical modifications.”

The first production aircraft, MH801, flew in November 2008 and the power problem soon became apparent, prompting confirmation of an engine upgrade in May 2010. Designated CT7-8A7, the new engine, developed at GE’s expense, generates 10 percent more power with a redesigned fuel manifold and nozzles, among other modifications. In the meantime, the “interim” aircraft have CT7-8A1 engines.

The Cyclone project dates to the mid-1980s, when DND acknowledged the need to plan on replacing its fleet of 1960s-era Sikorsky CH-124 Sea Kings. But it would be years before the need for Sea King replacements became urgent. In 2008-2009, the federal government awarded a contract to Sikorsky to begin delivering 28 aircraft. It also opted to purchase 15 EH101s from AgustaWestland for DND’s search and rescue (SAR) work, and those CH-149 Cormorants remain the backbone of coastal SAR today.

Nearly a year before the first Cyclone was to be delivered, Sikorsky sought “schedule relief” because of what it called “excusable” issues with the project. Then, about the time the first aircraft had been originally expected, DND and PWGSC agreed to a new schedule, which would see deliveries of “interim” platforms in November 2010 and fully compliant helicopters by June 2012.

That amended contract, which involved no penalties for Sikorsky, also saw the cost of 28 helicopters increase by more than five percent to some $1.9 billion US. Then, in late 2009, Sikorsky advised that it could not deliver a fully compliant helicopter by the new deadline. The contract was amended again in June 2010, providing for delivery of the first six aircraft with preliminary mission software by that November. A short time later, however, Sikorsky said first delivery would not take place until possibly February 2011, which eventually was pushed back yet again, to May 2011, when MH 806 arrived at Shearwater.

DND’s current but anodyne position is that it “continues to closely monitor progress” with a view to taking formal delivery of a fully compliant interim aircraft this year.
So in addition to the failure to meet various feature KPPs, this confirms the issue with engine power.
SansAnhedral is offline