Arrow Army mothballs Apache

from the BBC

Dozens of the Army's new £3bn Apache attack helicopters will be kept in storage for four years due to a shortage of trained pilots, the government's spending watchdog has said. Eleven of the 25 helicopters so far delivered - out of an order for 67 - have been mothballed in a move described as "wasteful" by the National Audit Office.
The NAO's report warned that although the Apaches were being delivered on time, a private finance initiative (PFI) deal to train aircrew was three years late.
Shadow defence secretary Bernard Jenkin blamed the government for the delays. "The delays in this programme mean that we have more than an entire squadron of attack helicopters sitting in sheds. They should be flying by now," he said.

The delay means dozens of aircraft will have to be stored away in hangars while the completion date for the initial training programme for 144 pilots is put back from April 2004 to February 2007.
The NAO warned the delay in training also put in jeopardy the delivery of 16 more Apache helicopters, scheduled for February 2005. That would reduce the Army's capability, it added. Contractual problems over the supply of spares could mean the Apaches kept in storage may have to be used for parts.

The initial order for 67 Apaches, placed with Westland Helicopters in 1995, was said to offer the greatest advance in Army effectiveness since the tank. A separate PFI agreement was reached with ATIL - a company jointly-owned by Westland and the Apache's US manufacturer Boeing - to cover the training. But delivery of the hi-tech flight simulator was delayed by 17 months, pushing the start date for pilot training from 2001 to September 2003.
The length of the training courses has been extended from 15 weeks to 26, because of the £45m helicopter's complexity and the UK's poor weather conditions for flying.
As a result, the NAO said a "large number" of Apaches - some estimates say more than half - will have to be stored away in hangars at RAF Shawbury in Shropshire at a cost of £6m. Out of the 25 helicopters delivered so far, 11 have been mothballed.
The head of the NAO, Comptroller and Auditor General Sir John Bourn, criticised the decision to split the training programme from the main contract. He said: "It is disappointing that because of problems with the training programme the helicopters are not expected to provide a brigade-level capability until February 2007."
The MoD said it had noted the NAO's concerns and steps were being taken to try to reduce the duration of the pilot training courses without compromising the quality.