The Facts!

  • The Roo's Heavy Maint H245 B744 'D Checks' completed in 36 Days
  • Only maint provider with nil, read NO, test flight requirement
  • Straight out of the shed to the eng run up bays, then off to LAX with full pax load
  • Exit maint delays, virtually nil
  • The 'MoU' MRO SE Asia, Heavy Maint B744 'D Checks' scheduled 55 Days
  • 27 'D Checks' back to back' before an on time exit achieved, then back to business as usual
  • Test flight requirement mandatory, wonder why?
  • The record of failed test flights, on one aircraft prior return to service, 5.
  • Average out of service time, 62.5 days.
  • Management have acknowledged closing H245 was a grave mistake, that could not be reversed. On the grounds of both cost and most importantly quality.