This is for all the CASA investigators and media out there....its simple
Go back to a QF done D check, look at the check component and more importantly the number of hours spent fixing problems found.
Look at the external MRO and compare the numbers, if they do 1/5th of the extra hours ill eat my hat.
We had workshops and support for all these avtivities today we have nothing left.
Go on ask the question it just so easy to catch these fools out. All those defects not fixed are the swiss cheese of the future. We have been so lucky with total power shut down 15min from landing and the oxy bottle that explodes for the first time ever in history...lets hope we are always lucky....never forget Mr Murphy and his laws!!!!!!