Phil,

The trent 800 FMU is not capable of recording its own positions, however, it will generate a demand discrepancy should the actual vs demand position for the Metering Valve be different. Parameters for the FMU are recorded elsewhere, see post below.

The Spill Valve is built into the FMU, and moves in accordance with the scheduled increases/decreases. As the report says, the FMU's both worked properly on test, therefore, they will have worked properly on the A/C, *if* they were provided with the correct delivery from the pump.

Last edited by RO13ERTS; 21st Feb 2008 at 18:50. Reason: accidently implied no parameters were recorded