That's me told then.....by Royalty too!

WEBF - Govan will probably start cutting steel summer 08 as their block is the largest and has to be in Rosyths dock first. VT are busting a gut to clear their shed of T45 bits before they start doing their export corvette and OPVs for Oman and T&T. Just where they're going to get the upper blocks built with sufficient outfit content eludes me at the minute.

The main LL items are the electric motors and diesels for installation in the lower machy spaces and should already be on order as part of the MG part 1 cash release a couple of years ago. Funnily enough the only executed equipment contract appears to be for the SIFF, which one might have thought could have waited.