Ameco Beijing held new Hangar Construction Design & Bid meeting on May 30th. 4 design companies from China, Germany and England presented their schemes and answered questions. GM & CEO He Li and GM Dr. Schmitz of Ameco Beijing, plus other
related leaders and appraisal experts attended.
It¡¯s said 7-person review committee will judge the submitted five schemes. Top leadership of Ameco Beijing will finally decide which company will be authorized due to the appraisal result.
The new Hangar locates at north of the new No. 3 Terminal Building. It¡¯s the accessory item to the Capital Airport Extension Project. The new Hangar adopted whole steel structure. The total construction area is about 50 thousand square meters. 2 A380s, 2 Boeing 747-400 and 2 Boeing 777-300ER can be maintained at the same time. There¡¯s one bay especially for aircraft
cleaning. The scheduled investment is 0.5 billion RMB.
It¡¯s planned that the original design plus shop drawing of this new Hangar will be completed before this Nov. 15th. The entire project will be arranged to finish before Oct. 30th, 2007.