Money starts flowing for new GCAP fighter, as Britain sorts out finances
ROME — Italy, Japan and the U.K. have signed a stopgap contract to keep work going on their joint GCAP fighter program for three months, giving the U.K. time to free up more funding.
The joint program office created by the three nations announced the signing of a £686 million ($906 million) development contract on Thursday with Edgewing, the joint venture set up to develop the sixth-generation jet by local champions BAE Systems, Leonardo, and Japan Aircraft Industrial Enhancement Co. Ltd. (JAIEC).
“The £686 million contract invests in key design and engineering activities and enables the trilateral partnership to build momentum and accelerate pace of delivery,” the tri-government GCAP agency said.
Edgewing’s first contract follows growing concern over delays in funding caused by ongoing uncertainty over the U.K.’s Defense Investment Plan, which was due to contain GCAP cash.
...
A source on the program told Defense News the new contract is a “bridge” allowing work to continue until the end of June, when it is hoped the U.K. spending plan will be complete and a second, larger contract can be signed.
...
To date Italy, the U.K. and Japan have created separate funding for the program. The new contract is the first time they have signed a single contract with Edgewing.
“This is the first time in history that responsibility for the technical design and development of a combat aircraft program has been fully vested in a new international prime contractor, and we are making every effort to live up to this responsibility.” said the Edgewing spokesman.
Masami Oka, GCAP Agency Chief Executive said, “This contract is an important moment for GCAP, as activities previously conducted under three nations’ contracts will now be carried out as part of a fully-fledged international program.”