F-35 Program Achieves Milestone C and Full Rate Production 12 Mar 2024
https://www.f35.com/f35/news-and-fea...roduction.html or
https://www.defense.gov/News/Release...te-production/
"Earlier today, the Milestone Decision Authority, Under Secretary of Defense for Acquisition and Sustainment, Dr. William A. LaPlante, approved the
Milestone C / Full Rate Production (MSC/FRP) of the F-35 Lightning II aircraft with the signing of an Acquisition Decision Memorandum (ADM) after a meeting with the Defense Acquisition Board (DAB)...."
PHOTO: https://www.f35.com/content/dam/lock...-35BHeadOn.jpg
_________________
"...The decision came more than
four years after the Pentagon originally planned, and followed multiple years of delays due to troubles setting up the necessary Joint Simulation Environment tests...."
https://www.defensenews.com/air/2024...te-production/
_____________________
"...Although the designation is in some ways moot—the F-35 production enterprise is already operating at a rate close to its capacity—the designation means the Joint Program Office can now negotiate
multiyear contracts for the fighter...."
https://www.airandspaceforces.com/f-...te-production/
_____________________
"The Pentagon has finally approved the F-35 Joint Strike Fighter for full rate production,
five years later than originally anticipated...."
https://breakingdefense.com/2024/03/...-5-year-delay/