Originally Posted by pitchlink
I am looking for the AW139 TCCA procedure that used to be available for the AW139 electrical fire (Not sure if it is still approved)? It involved pulling a whole heap of CBs to isolate the Essential busses if I remember correctly. Does anyone out there have a copy they could share?

To isolate MB2 Pull Bus Contr1 and Bus Contr2 breakers, THEN turn off GEN 2, this to prevent the BUS TIE from closing automatically (Bus contr1 and Bus contr2 control the BUS TIE logic)
To isolate MB1 flip Battery Main OFF and of course GEN 1 OFF.
To isolate ESS 2, pull the Ess TIe CB and Auxiliary Battery CIRCUIT BREAKER, as opposed to one large North Sea operator emergency checklist that have you turn off the Auxiliary Battery switch (it has been many years, hopefully they finally caught the mistake after refusing to make the change following repeated suggestions).
Essential 1 is not isolated that's why TCCA has mandated color coded breakers collars.
Procedure is a great toll to learn electrical system functionality, but in the real world just put it down somewhere safe.
Are you telling us that the yellow Canadian pages have gone from the Electrical Fire checklist?