Originally Posted by
RW20
Can I ask where you got this info from?,latest email from the construction team is mid August for completion ,so official opening in September seems rather optimistic !
Sorry to be pedantic, what is defined as “completion”? If I were AGS I am not going to pay the final invoice until my surveyors have confirmed that I have the 164 metres that I am paying for, the runway markings are in accordance with plans approved by CAA and the AGL changes are firstly in accordance with the CAA approved project plans and secondly have been successfully flight checked. That’s what I’d define as “completion”.
In line with my definition I’d be planning the official opening in September.