It looks like this month is the right time for a new thread where we can debate

and rumour

about UK helicopter SAR and occasionally marvel at the durability and longevity of the RAF vs RN posh-hovering bitch-fest.
The UKSAR2G contract process was due to kick off this week but the nominated date has come and gone without comment.

Whatever happens, they need to get it moving in the next few weeks.
An engagement phase has been progressing since last spring involving interested parties in the industry and SAR stakeholders including police, MRT, lifeboats, ambulance, fire and others. That phase has included
several online meetings with Q&A sessions and consultation on draught copies of key documents.
At an early stage in 2012 there emerged a technical requirement matrix that was largely inherited from SARH25. The approach this time moves towards 'effect-based requirements'. Qinetiq's Post Implementation Report in 2019 proposed the development of 'Measures of Effectiveness' and such measures are now set against each 'User Requirement' in the form of a Threshold value and an Objective value
The latest versions of the Lot descriptions appear in the
recent Prior Information Notice and you may find those enlightening.
Here are the published dates for the contract process based on documents on
the UKSAR2G webpage and the Prior Information Notice published last Wednesday.
Publication of Procurement Notice 25 Jan 2021
Publication of Selection Questionnaire & Memorandum Of Information 25 Jan 2021
Deadline for Submitting Clarification Question on MOI & SQ 1 Mar 2021
Deadline for responses to MOI &SQ 8 Mar 2021
SQ Evaluation & Shortlisting & Assurance 19 Apr 2021
Notification of Decision to Candidates 26 Apr 2021
Issue of ITT to Participants 4 May 2021
Deadline for Submission of Initial Tenders 9 July 2021
Evaluation … Shortlisting for Participation in Negotiation 20 Sep 2021
Negotiations 21 September to 29 November 2021
Issue of Invitation To Submit Final Tender (ITSFT) 29 Nov 2021
Deadline for Submission of Final Tenders 15 Jan 2022
Evaluation of Final Tenders 18 Feb 2022
Government Internal and Assurance Process 18 Feb 2022 to 4 Jul 2022
Award Decisions 5 Jul 2022
Standstill Letters Issued 5 Jul 2022
Contract(s) Completed With Supplier(s) 26 Jul 2022

Contract extensions have recently been awarded for both rotary and fixed wing existing contracts. The mobilisation phase is now scheduled to run until 30th September 2024. (Originally, the current rotary contract had been due to start transitioning out in 2023.) The entire contract is due to be established in service by 31st December 2026. As I understand it, the latest date that any part of the current rotary contract can be extended to is 31st March 2028.