Construction update

The passenger footbridge over the tracks at Parkway has received its first escalator to the platforms below.


The photo shows the Dart trackbed. Either side of the bridge can be seen 3 V shapes. These are the approach lights to runway 07


Taxiway Bravo is being reinstated with the tunnel below.


With the tunnel complete the last section of infilling is taking place by the terminal station entrance.


The passenger walkway over the terminal station has now been concreted with the roof supports underneath taken away.


Lift shafts and stairwells are going in.