Re the new hospital being built in Wuhan: News reports say they aim to have it finished and equipped within 10 days! 10 days for a 1,000 bed hospital. And they have form, they did the same in Peking for the SARS outbreak.
Meanwhile, look at the fiasco at the Royal Liverpool hospital, not Carillion's finest hour! Still not completed, estimated completion date is now 2022, 5 years late! "difficulties" both during and post Carillion's involvement included surveys that revealed concrete beams were rubbish and had to be ripped out and reinstalled. And the plumbing, electrical wiring, external cladding etc etc. All found to be gash and needed urgent remedial actions.