For those who may be interested the relevant OAN is:

OAN 96/2019 – MAN-TP PIER 2 AIRSIDE SURVEYS
OAN REF:- 96/2018 DATE OF ISSUE:- 02/10/19 EFFECTIVE DATE:- 14/10/19 EXPIRY DATE:- 25/10/19
1.0 SUMMARY
1.1 A series of non-intrusive topographical, GPR and utility surveys will take place in advance of works to construct the new Terminal 2 Pier 2. 2.0 PROGRAMME, LOCATION & OPERATIONAL IMPLICATIONS
2.1. Overall, from Monday 14th October until Friday 25th October 2019. Working Monday to Friday 09:00- 17:00L


3.0 SCOPE OF WORKS
3.1 The scope of works is:
• Lifting of service chambers covers for visual inspection and recording of services.
• Ground Penetrating Radar (GPR) survey of all areas.
• Topographical survey of all areas.
4.0 PUSHBACK PROCEDURES
4.1 ATC may need to issue non-standard pushback procedures for some Terminal 2 stands when the survey works on Taxiway Delta are in progress.
5.0 LOW VISIBILITY OPERATIONS (LVO)
5.1 The works will have no effect on Low Visibility Procedures. Work in LVPs at the ADMs discretion. -