Central Station continues to be dug out. Under construction multi story to the right, new de-icing pads and taxiway in the background.
Meanwhile at the other end of the line Parkway Station interchange is progressing well. The trackbed will be on the first floor.
The 5 sections of the Gateway Bridge are being wielded together.
By Taxiway Bravo a section of roof has been installed over the trackbed which will allow the taxiway to be diverted over it.
The second multistory has now reached the third core. With no missing sections of fencing maybe the bridge to link both car parks has been abandoned as drawings showed a bridge to the left of the core.
The new parallel taxiway to Delta and the de-icing pads are nearing completion.