Temporary Taxiway Bravo diversion has had concrete laid either side of the dug out route for the Dart which now needs a roof in this section to complete the taxiway.
Meanwhile just inside the CTA the full depth of what will be the tunnel can be seen where the rams are. The Dart Tunnel seems it might be a lot deeper than the road tunnel entrance to its right.
MSCP2 has now reached the main lift core
Meanwhile at Luton Airport Parkway the Dart Station is having temporarily trusses installed to take the weight of the floor above which will be installed later.