Bend alot 14th Dec 2019 01:39

The numbers really do not add up for aircraft to to have not been delivered - that is a massive amount of stock to be holding, but it might be true.

I also think in the last hearing it was said that aircraft were delivered.

This from Tom.

In June, FAA safety engineer Thomas Thorson, concerned that his agency was hurriedly approving Boeing’s desired changes, formally objected.

“I do not agree that delivery schedules should influence our safety decisions and areas of safety critical findings, nor is this consistent with our safety principles,” Thorson wrote, adding the agency’s technical experts had discovered errors in the way Boeing summed up the various risks of the lightning protection features and that with the removal of the foil “the fuel tank ignition threat … cannot be shown extremely improbable”.

Thorson estimated that if the methodology was corrected, the ignition risk “would be classified as potentially unsafe”

tdracer 14th Dec 2019 03:09


Originally Posted by Bend alot (Post 10639414)
The numbers really do not add up for aircraft to to have not been delivered - that is a massive amount of stock to be holding, but it might be true.

I also think in the last hearing it was said that aircraft were delivered.

Thorson estimated that if the methodology was corrected, the ignition risk “would be classified as potentially unsafe”

40 wing sets is less than three months production. Given wings and aircraft in assembly, units in inventory and transit (the wings are built in Japan), and completed aircraft going through pre-delivery processing, 40 is far from "massive". Further, delivery pre-cert would be a major escape - the sort of thing that gets production shutdown and it wouldn't be a rumor.

"Thorson estimated" - so a non-lightning specialist, with only a passing knowledge of the methodology in question, estimated. Hardly a convincing argument that the aircraft are unsafe.



Bend alot 14th Dec 2019 04:28


Originally Posted by tdracer (Post 10639433)
40 wing sets is less than three months production. Given wings and aircraft in assembly, units in inventory and transit (the wings are built in Japan), and completed aircraft going through pre-delivery processing, 40 is far from "massive". Further, delivery pre-cert would be a major escape - the sort of thing that gets production shutdown and it wouldn't be a rumor.

"Thorson estimated" - so a non-lightning specialist, with only a passing knowledge of the methodology in question, estimated. Hardly a convincing argument that the aircraft are unsafe.

There will be no more than 12 in the production line as the maximum delivery was around that amount - 145 deliveries in a year.

So we have 28 wing sets waiting around?

Given the fact of the size of the wings built in a location far from assemble area, a smart and cost cutting company will be holding low stock levels.

Delivery times for the 787's wings, built in Japan, will be reduced from around 30 days to just over eight hours with the 747 LCF. from wikki.

Realistically anything over 30 days stock would be excessive.

Your words on Thorsen gave him credit for being intelligent - so given facts, he could see what classification the data presented should fall into.
The data presented did not meet the classification Boeing gave it, the same thing happened with the MAX and MCAS.

The wrong classification was given.

Thorson wrote, adding the agency’s technical experts had discovered errors in the way Boeing summed up the various risks.

"Further, delivery pre-cert would be a major escape - the sort of thing that gets production shutdown and it wouldn't be a rumor." Again missing required AOA warning on the MAX as to Boeings concern of any shutdown happening from FAA ever.

A year ago many of us would ever have given a thought of Boeing ever doing such a blatant and illegal act, that has changed to highly probable.

Dave Therhino 14th Dec 2019 06:15

[QUOTE=tdracer;10639358]The 787 has a copper mesh embedded in the carbon fiber matrix - the wing, fuselage, pretty much everywhere. In addition - due in part to the uncertainties in the lightning characteristics of carbon fiber - they added a metallic copper foil to the inside of the wing skin. Once they had real aircraft structure to test and analyze they were better able to quantify the lightning threat. /QUOTE]

There is no copper mesh in the 787 wing composite panels. You might be remembering some of the early design concepts that were discussed, but the final design has no copper mesh. The foil was on the outside surface in strips along the fastener rows, not on the inside, and was there to reduce the current driven through a fastener if lightning attached to or near that fastener. It provided a fail safe feature such that, if one of the other fastener features deteriorated or was left out in production, they still avoided an ignition source. They eliminated the foil because it was so troublesome to repair following a lightning strike, and they were willing to eliminate fail-safety in the design. The FAA staff objected to that.

Airbus doesn't have foil because they have copper mesh, which is pretty much the industry standard.

It's not at all fair for you to label Tom Thorson "reasonably sharp" as though you are much more intelligent than he is. His role is completely different from what yours was. He has to cover over a dozen different propulsion technical disciplines and their applicable regulatory and policy requirements, and he is knowledgeable in every one of them to an impressive depth. He also has working knowledge of airframe structural requirements, airplane performance requirements, systems requirements, structured system safety analysis, and environmental noise and emissions requirements. He is extremely hard working and dedicated. He worked on the space shuttle propulsion system before he worked for Boeing and later the FAA. You worked in a much narrower area for 35 years and became a deep expert in that area. I always respected your intelligence, knowledge, skills, and judgment, but don't damn Tom with faint praise. He has knowledge and experience in areas you aren't aware of. He's also very reserved and doesn't say much until he's sure about what he's saying. "Reasonably sharp" does not do him justice.

UltraFan 14th Dec 2019 06:53

A question to the physicists among us. I keep hearing that Boeing and Airbus had to do some serious rethinking of lightning protection because the composite structure doesn't form the Faraday cage that the aluminium fuselage forms. It is my understanding, however, that carbon fibre is excellent conductor. And I can actually concur - the cores of my HD leads are made of it. Hence the aircraft structure made of carbon fibre reinforced composite should be a perfect conductor. So what exactly is the problem there? Carbon fibre doesn't form a Faraday cage? Or is that it's too good a conductor? Could someone please explain?

GordonR_Cape 14th Dec 2019 08:50


Originally Posted by UltraFan (Post 10639510)
A question to the physicists among us. I keep hearing that Boeing and Airbus had to do some serious rethinking of lightning protection because the composite structure doesn't form the Faraday cage that the aluminium fuselage forms. It is my understanding, however, that carbon fibre is excellent conductor. And I can actually concur - the cores of my HD leads are made of it. Hence the aircraft structure made of carbon fibre reinforced composite should be a perfect conductor. So what exactly is the problem there? Carbon fibre doesn't form a Faraday cage? Or is that it's too good a conductor? Could someone please explain?

Short answer: The fibers in carbon composite are not continuous, but embedded in a non-conducting polymer matrix.

tdracer 14th Dec 2019 19:54


Originally Posted by Bend alot (Post 10639455)
There will be no more than 12 in the production line as the maximum delivery was around that amount - 145 deliveries in a year.

So we have 28 wing sets waiting around?

Given the fact of the size of the wings built in a location far from assemble area, a smart and cost cutting company will be holding low stock levels.

Delivery times for the 787's wings, built in Japan, will be reduced from around 30 days to just over eight hours with the 747 LCF. from wikki.

Realistically anything over 30 days stock would be excessive.

OK, let's do some math. 787 production rate is 14 aircraft per month - split evenly between Everett and Charleston. At any particular time, there are 7-8 aircraft in various stages of final assembly - at each line. So between Everett and Charleston that's 14 - 16 wing sets. Once they push a new 787 out the door, it's far from ready for delivery - it has to be painted, go through various functional tests and fueling/defueling checks, production acceptance flight tests, customer acceptance flight tests, and the actual ticketing and delivery. While I've heard of this taking as little as two week, four to six weeks from rollout to delivery is more typical. Last time I overlooked the Everett flight line, there were at least 12 787s parked there. I've not seen the Charleston flightline, but I have no reason to expect it would be much different, so that's around another 24 aircraft. Add it up and we're looking at 38-40 wing sets - without accounting for any inventory, wings currently being produced, or units in transit. In fact, 40 shipsets is right about where I'd expect it to become an delivery issue if the change wasn't certified. Which, interestingly, is pretty much what's described in the linked article.

Dave, sorry if referring to Tom as "reasonably sharp" came across as condescending or insulting - that certainly was not my intent and I apologize if it came across that way. Tom is very competent (unlike a few other FAA types I dealt with) - my point being he's a Propulsion specialist, which in itself covers a wide range of issues. You can't expect him to be an expert at lightning as well. That's why Boeing has an EMI/Lightning group made up of experts in the field that support the various other disciplines so that they don't need to be EMI/Lightning experts.

Are you sure about the lack of copper in the 787 carbon fiber matrix? Because that's certainly contrary to what I was told by my co-workers who were on the 787 program. It also creates lightning concerns unrelated to fuel tank ignition. While carbon structure is a reasonably good conductor, it's electrical resistance is still an order of magnitude worse than aluminum structure - which greatly increases the induced voltages/currents on the aircraft wiring when a lightning strike passes through the surrounding structure - so copper was added to lower the electrical resistance and keep the induced levels reasonable. I know the the systems on the 787 were certified for higher lightning transients relative to primarily aluminum aircraft (such as 777 and 747-8), but those levels were still lower than what would have been required if it was pure carbon without any additional conductive material added to the matrix.

archae86 14th Dec 2019 20:18

One snapshot
 

Originally Posted by Bend alot (Post 10639455)
There will be no more than 12 in the production line as the maximum delivery was around that amount - 145 deliveries in a year.

So we have 28 wing sets waiting around?

Given the fact of the size of the wings built in a location far from assemble area, a smart and cost cutting company will be holding low stock levels.

Delivery times for the 787's wings, built in Japan, will be reduced from around 30 days to just over eight hours with the 747 LCF. from wikki.

Realistically anything over 30 days stock would be excessive.

I don't know on what date the spreadsheet was updated, nor do I know the author's sources, but believe him to have been publishing reasonably accurate 787 data for years.

Uresh, publishing at All Things 787
The lines of the spreadsheet of relevance to this discussion which show non-zero entries as of the update are:

11 Undergoing final Assembly
7 Pre-flight prep
16 production testing
5 ready for delivery

That does not cover the pipeline back before actual final assembly, but that pipeline is nothing like a few hours in length. (I used to work in a different line of high-tech manufacturing).

Bend alot 14th Dec 2019 21:16


Originally Posted by tdracer (Post 10639977)
OK, let's do some math. 787 production rate is 14 aircraft per month - Once they push a new 787 out the door, it's far from ready for delivery - it has to be painted, go through various functional tests and fueling/defueling checks, production acceptance flight tests, customer acceptance flight tests, and the actual ticketing and delivery. While I've heard of this taking as little as two week, four to six weeks from rollout to delivery is more typical.

Two weeks will also need to be as typical as six weeks, not an exception to equal 14 deliveries.

Bend alot 14th Dec 2019 21:24


Originally Posted by archae86 (Post 10639990)
I don't know on what date the spreadsheet was updated, nor do I know the author's sources, but believe him to have been publishing reasonably accurate 787 data for years.

Uresh, publishing at All Things 787
The lines of the spreadsheet of relevance to this discussion which show non-zero entries as of the update are:

11 Undergoing final Assembly
7 Pre-flight prep
16 production testing
5 ready for delivery

That does not cover the pipeline back before actual final assembly, but that pipeline is nothing like a few hours in length. (I used to work in a different line of high-tech manufacturing).

The link did not work for me.

The ready for delivery of 5 I assume is over both plants?

archae86 14th Dec 2019 21:53


Originally Posted by Bend alot (Post 10640036)
The link did not work for me.

The ready for delivery of 5 I assume is over both plants?

Sorry about the link--I don't seem to know how to get the site software not to mangle it. I actually used the editing command to insert a link, and at the time I did so it showed appropriate text for both the display text and the actual URL. But that is not what the site posted in my name.

You may find that simply typing:
All Things 787
Into a browser will show you the place which is published at a location the PPrune site software censors for me, which includes the components "blog" and "spot".

Each of the numbers shown is summed over the two final assembly locations--so yes to your question.

Grebe 14th Dec 2019 22:59


Originally Posted by tdracer (Post 10639977)
OK, let's do some math. 787 production rate is 14 aircraft per month - split evenly between Everett and Charleston. At any particular time, there are 7-8 aircraft in various stages of final assembly - at each line. So between Everett and Charleston that's 14 - 16 wing sets. Once they push a new 787 out the door, it's far from ready for delivery - it has to be painted, go through various functional tests and fueling/defueling checks, production acceptance flight tests, customer acceptance flight tests, and the actual ticketing and delivery. While I've heard of this taking as little as two week, four to six weeks from rollout to delivery is more typical. Last time I overlooked the Everett flight line, there were at least 12 787s parked there. I've not seen the Charleston flightline, but I have no reason to expect it would be much different, so that's around another 24 aircraft. Add it up and we're looking at 38-40 wing sets - without accounting for any inventory, wings currently being produced, or units in transit. In fact, 40 shipsets is right about where I'd expect it to become an delivery issue if the change wasn't certified. Which, interestingly, is pretty much what's described in the linked article.

Dave, sorry if referring to Tom as "reasonably sharp" came across as condescending or insulting - that certainly was not my intent and I apologize if it came across that way. Tom is very competent (unlike a few other FAA types I dealt with) - my point being he's a Propulsion specialist, which in itself covers a wide range of issues. You can't expect him to be an expert at lightning as well. That's why Boeing has an EMI/Lightning group made up of experts in the field that support the various other disciplines so that they don't need to be EMI/Lightning experts.

Are you sure about the lack of copper in the 787 carbon fiber matrix? Because that's certainly contrary to what I was told by my co-workers who were on the 787 program. It also creates lightning concerns unrelated to fuel tank ignition. While carbon structure is a reasonably good conductor, it's electrical resistance is still an order of magnitude worse than aluminum structure - which greatly increases the induced voltages/currents on the aircraft wiring when a lightning strike passes through the surrounding structure - so copper was added to lower the electrical resistance and keep the induced levels reasonable. I know the the systems on the 787 were certified for higher lightning transients relative to primarily aluminum aircraft (such as 777 and 747-8), but those levels were still lower than what would have been required if it was pure carbon without any additional conductive material added to the matrix.

TDracer- perhaps part of the confusion comes from dates of changes in the production process such that both answers regarding copper mesh and conduction and lightning strikes are ' correct'

The Seattle Times: Business & Technology: Building the 787 | When lightning strikes

Is a great explanation as to what WAS about 12 years ago.
this partial quote from the article re Walt Gillette is a great summary as it applied THEN.


Engineers in Everett are debating the best way to achieve that outcome for a largely plastic airframe. In November, one top safety-engineering team expressed serious concern.

That team's internal review, obtained by The Seattle Times, concluded: "It cannot be shown that the current wing-lightning-protection approach will preclude ignition sources in the fuel tank."

Walt Gillette, who leads the 787 engineering team as Boeing's vice president of airplane development, said the review was part of a healthy internal debate that ultimately assures the best engineering solution.

Composites are not new in commercial aviation, he said. And although the safety team's conclusion was "absolutely true at the time" it was written, he said, by the end of the testing and analysis now in progress, the 787 will meet strict Federal Aviation Authority (FAA) requirements. . . . , , , Typically, a bolt moves backward across a wing or fuselage before the charge exits to the ground milliseconds later. At the point of entry on a metal skin, the aluminum can melt, leaving a pitted surface or a small hole.

"You can't hit aluminum with 200,000 amps and expect nothing to happen," Gillette said. "But it's not a safety-of-flight issue."

On the composite fuselage of the 787 a strike is unlikely to penetrate more than the outer layers of carbon fiber.

Such damage needs repair but is not a big deal. More serious is the possibility that the electric charge passing through the airplane will create a spark inside the wing, potentially causing a fuel-tank explosion and destroying the aircraft.

. . . Gillette said his team is perhaps only months away from agreeing with the FAA on an overall 787 certification plan, which will include proving that the risk of a lightning-induced fuel-tank explosion is less than one in a billion.

"When it's all done, the end of a five-year process ... the FAA will evaluate all that we have done," Gillette said, "and they will find that we have met the rule."

Of course that was THEN - Walt has since retired.

There were similar problems on the B2- as to level of protection- and Walt was there. And from memory and not classified, ALL of the B2 was rated at the highest level of protection.





tdracer 14th Dec 2019 23:00


Originally Posted by Bend alot (Post 10640029)
Two weeks will also need to be as typical as six weeks, not an exception to equal 14 deliveries.

Your assumption is flawed. Production rate does not equal delivery rate over the short term. The production rate is reasonably constant month to month, for what should be obvious reasons. Delivery rate varies dramatically month to month for a variety of reasons. A major reason is that operators tend to want to take delivery at certain times of year - such as right before the big summer season, and not want to take delivery in the middle of the winter when traffic is slow (their own version of 'just in time' supply). Since it's not feasible to produce 8 aircraft one month, and 20 the next, they do what's known as 'build ahead' - the aircraft are tested and prepped for delivery, then parked for a month or more until the operator is ready to take delivery.

swh 15th Dec 2019 00:07


Originally Posted by tdracer (Post 10639374)
If metal foil external to the carbon fiber structure is so important, why isn't it needed on the A350? According to what Less Hair posted, they embed copper mesh - just like Boeing - no mention of external foil in the fuel tanks...

Remember the jokes 30 years ago when people would boast that they flew a metallic Boeing, and Airbus builds plastic aircraft ? Like it or not Airbus does have more extensive in service experience with composite aero structures in commercial aviation.

Airbus addressed these issues from the outset in the initial design testing and certification (they actually subjected a test airframe to numerous lighting strikes in the fuel tank area) to and has not changed the way to builds the wings. There is detail design differences between the way the two companies addressed the issues. The A350 wing was designed with the experience they had developed on the A380 HTP and the A400 wing.

The issue here is that Boeing went off reservation and starting building wings that did not conform to the original certification basis without first getting the new certification basis. This represents issues with the production certificate as well as the type certificate.

This is the second production certificate issue I have heard in a week, the other being a 737 wing part identified by the subcontractor as being non conforming ending up on assembled civil and military airframes.

Dave Therhino 15th Dec 2019 01:08


Originally Posted by tdracer (Post 10639977)

Dave, sorry if referring to Tom as "reasonably sharp" came across as condescending or insulting - that certainly was not my intent and I apologize if it came across that way. Tom is very competent (unlike a few other FAA types I dealt with) - my point being he's a Propulsion specialist, which in itself covers a wide range of issues. You can't expect him to be an expert at lightning as well. That's why Boeing has an EMI/Lightning group made up of experts in the field that support the various other disciplines so that they don't need to be EMI/Lightning experts.

Are you sure about the lack of copper in the 787 carbon fiber matrix? .

Thanks for the further comment about Tom.

Yes I'm sure about no mesh in the wing skins. I know mesh was seriously considered and I believe it was part of the planned configuration for some time, but I believe concerns about delaminations and difficult repairs after lightning attachments led to the decision to go without mesh.

Bend alot 15th Dec 2019 07:46


Originally Posted by tdracer (Post 10640095)
Your assumption is flawed. Production rate does not equal delivery rate over the short term. The production rate is reasonably constant month to month, for what should be obvious reasons. Delivery rate varies dramatically month to month for a variety of reasons. A major reason is that operators tend to want to take delivery at certain times of year - such as right before the big summer season, and not want to take delivery in the middle of the winter when traffic is slow (their own version of 'just in time' supply). Since it's not feasible to produce 8 aircraft one month, and 20 the next, they do what's known as 'build ahead' - the aircraft are tested and prepped for delivery, then parked for a month or more until the operator is ready to take delivery.

So you will agree aircraft ready for delivery are fully complete and signed off ready for service?

Or there is more to be done, such as certification to fly or export?

Current documented (I did not access the above) was 5 units of the "build ahead" over both plants - you implied that had grown to 12 in one plant from your observation and assumed it was 24ish over both plants.

Well we now know why the cut in deliveries was announced - too much stock on hand..

Grebe 15th Dec 2019 20:38

How did we get from lightning strike issues to a discussion of factory firing (assembly) rates, stations, schedules , delivery rates, sales, financing, shoulda rates, coulda rates, and how many angels on the head of a pin ? :*

asw28-866 15th Dec 2019 22:38

Grebe, PPRune first law of threading:

Coefficient(Thread Drift) = 1/(Airbus or Boeing) * (Posts Squared) * Contributors

matkat 16th Dec 2019 10:27


Originally Posted by SLF3 (Post 10637150)
Without wishing to start Boeing versus Airbus debate, does the A350 have the foil in the wings?

The question is only because, if the wing construction is broadly similar and EASA / Airbus require it, that is strong evidence that the FAA should have insisted.

Yes it does, it(The A350) has copper sandwiches embedded in the CRP wing.

turbidus 5th Jan 2020 19:03

"According to statistics published by the Royal Canadian Air Force, a plane can be struck by lightning on average every 1,000 to 3,000 flight hours. For commercial aircraft, that’s equivalent to one strike per aircraft per year.

Although The Boeing Co. (Chicago, Ill.) has reported that the probability of a worst-case strike could be as infrequent as once every 10 to 15 years, aircraft designs must be able to withstand such a strike.

Boeing recently reported in its AERO magazine that an airplane flies farther than its own length in the time it takes a strike to begin and end. Therefore, the entry point will change as the charge reattaches to other locations aft of the initial point. This can result in multiple burn areas or other damage that could have a direct effect on a plane’s structural integrity, and indirect effects that include damage to radio equipment and avionics or other electrically operated mechanisms, such as fuel valves when electrical potential differences or magnetic effects cause transient voltage spikes. Further, fatal accidents have occurred when current has arced around metal fasteners and ignited fuel vapors."

From my experience, I have been banged at least once a year if not more....so once a year is very conservative, and I think it is more often. Boeing claiming WORST CASE STRIKE (WTF does that mean??) is once every 10 to 15 years??? That has NOT been my experience.

IF the 787 is designed for a once in 15 year strike, there may be some valid concerns...

https://www.compositesworld.com/arti...osite-aircraft