PPRuNe Forums

PPRuNe Forums (https://www.pprune.org/)
-   Rotorheads (https://www.pprune.org/rotorheads-23/)
-   -   Dangers of Shockloading (https://www.pprune.org/rotorheads/395729-dangers-shockloading.html)

Ned-Air2Air 13th November 2009 06:12

Dangers of Shockloading
 
Some reading for you guys.

Dangers of shock loading

All helicopter pilots understand the dangers and difficulties inherent in aerial winching and hoisting. One of the less understood dangers is that of Shock Loading – loads which exceed the static load caused by rapid movement changes such as swinging, impacting or jerking. CHRIS SMALLHORN reports.


There was a time, not so long ago, when the critical risks associated with the shock loading of helicopter hoist wires were not appreciated. I recently spoke with a colleague who has working as a crewman in military and civilian helicopters for more years than he cares to remember. He told me of some of his early experiences doing cliff winching where taking shock loads on the hoist was not all uncommon. While not intentional, a slip of a person from a cliff edge, over-control of the aircraft in poor visual conditions or perhaps over-eager winching techniques with some of the older equipment, often resulted in sudden application of excessive loads, otherwise known as “shock loading.” The associated risks and just as importantly, why the risks exist – were not taught in training. I would like to think that throughout the helicopter industry, the cautions relating to shock loading during winching or hoisting have become well known. Even if this is so, one can never have too much information on the “whys?” and “what fors?” applicable to our craft. Hoisting of personnel from beneath a helicopter is a risky business at the best of times. To minimize the risks it is the responsibility of all operators to understand them, and more importantly, to understand what mitigations are available, whether by way of technique or engineering.

What is shock loading?
Let’s look at a few common engineering terms used in cable dynamics and loads. A cable has what is called in the engineering world a Working Load Limit (WLL) which is the maximum load that should ever be applied under any conditions. Note however, that the WLL is based on the load being uniformly applied in a straight line pull. The flight manual rated loads applied for operations takes this into account and you may be reasonably assured that the load limit in your flight manual is significantly less than the cable WLL.

The “Breaking Strength” is an average loading at which cable samples were found to break under laboratory conditions in straight line pull, using a constantly and predictable increasing load. The Breaking Strength is not used for design or cable load rating purposes – the WLL is used instead.
Shock Loads are those loads which exceed the static (or simple hanging/straight line) load, caused by rapid movement changes such as swinging loads, impacting or jerking. I would assume that all readers who are somewhat experienced in hoisting or winching missions are thinking, “Yep, I’ve seen each of those at some time.”

Steel cables, such as those used on helicopter hoists, are actually like a rope, in that they stretch – although to a far lesser degree. The amount of stretch is directly proportional to the length of cable deployed and the load being carried. The more cable that is deployed and the greater the load, the more physical stretch is exhibited by the cable. The more stretch that the cable is capable of undergoing, the more it is able to absorb shock loading. In short, the more cable deployed the more the cable can absorb shock loading, and the shorter the cable, the more susceptible the cable will be to damage or catastrophic failure from shock loading. This brings up an important note – arguably the most critical part of the winching process where shock loadings may occur is in the last few feet of the recovery. Here the rescue crewman and/or survivor are trying to access the cabin where it is most likely that a slip or fall may occur, imparting heavy shock loads to the cable. Furthermore, the shock loads in this position are also likely to have a lateral aspect, with a small swing developing. Maintaining little to no slack in the cable is imperative during this phase of the recovery.

The Math
In order to understand the magnitude of force that can be applied to a cable under a shock loading condition we must first explore the math and physics of the problem. In order to simplify, we’ll assume our cable acts like a simple spring. This is not a leaping assumption, but an engineering reality. The cable,
like a spring, has a spring constant defined by the amount of “stretch” or elongation that will occur for a given static weight. The spring constant is a measure of stiffness of the cable and is a fixed value for any given length of cable. A typical helicopter winch cable is a wound 3/16 inch steel cable. A reasonable figure to work with for our purposes is that the cable will stretch approximately 0.334% of the payed out cable length with a static 600lb (272.15kg) mass hanging from the hook.
The spring constant is calculated from two fairly simple (metric) formulae:

EQUATION 1
F = k*x
or
k = F/x
where
F = Force (in Newtons, N)
k = spring constant (in Newton per meters, Nm-2)
x = cable stretch or elongation (in meters, m)

Note that mass must be converted to force – so:

F = m*a (Newton’s Law)
where:
F = Force in Newtons (N)
m = mass in kilograms (kg)
a = acceleration in meters per second squared (ms-2) and in the case of a mass being affected by gravity, the acceleration value equals 9.8066 ms-2.

Our 272.15 kg mass therefore equates to a force of:
F = 272.15 * 9.8066 = 2668.87 N

For a 61 meter (200ft) cable with 0.334% cable stretch, the cable will stretch 0.2032 meters (8 inches)

Therefore, for that 61m cable:
k = F/x = 2668.87 / 0.2032 = 13134.18 Nm

If we plot force v. elongation, the slope of the curve remains linear until the cable reaches its elastic load limit. The elastic limit is the point at which the cable will no longer return to its original length after a load is removed. At the elastic load the cable is said to “yield”. Now, unlike a natural fiber rope, steel once it has yielded, actually elongates faster for a given increase in load than it did before yield. Therefore, exceeding a yield limit in a steel cable is not where we want to be, and manufacturers fortunately ensure the yield limit is sufficiently high that our static loads don’t come close.

Accordingly, we need only consider the linear portion of the curve. Note that the spring constant, k, varies for a given length of cable. Equation 1 (on the previous page) shows the amount of stretch or elongation for a static 600lb (272.15 kg) mass for varying lengths of payed out cable. Using Equation 1, Figure 2 shows the spring constant (k) for varying lengths of payed out cable. Note that the spring constant becomes exponentially larger, the shorter the payed out length of cable, which makes sense as the amount of force required to affect a given amount of stretch will increase dramatically for a shorter length of cable, as there is less available cable to stretch.
So as you can see, there is very little stretch in a cable, and critically, the amount of stretch is significantly less when the cable is shorter; but what little there is, is all important in the business of absorbing shock loading. The more stretch, the more energy absorption the cable can facilitate. The level of stretch controls the critical issue of deceleration of a mass once a shock load is “taken up.” That is to say, the time taken to slow down a load that is rapidly applied to a cable is less – the shorter the cable. The longer the cable, the more spring is evident, hence it will take slightly longer to slow down the load. The resultant rate of deceleration is all important when it comes to the magnitude of shock load that is applied to the cable. The magnitude of the loads can be extraordinary, as we will now calculate in Equation 2.

The term “shock loading” is, in the purist sense, a little misleading – but suitable for our purpose. If we think of a shock occurring in a very short period of time, that is in a fraction of a second, then we are on the right track. When a mass falls it builds energy. The mass is accelerating towards the ground, and for the short periods we are talking about, drag and friction are negligible. The mass accelerates towards the ground at the acceleration provided by gravity, that being approximately 9.8ms-2. So a mass accelerating towards the ground for half a second would be traveling at approximately 4.9ms-1. Note that in that half a second the mass would fall 4ft (1.2m), which is pretty extreme. Provided good cable management techniques are employed, it is highly unlikely to occur except possibly on yacht rescues.

Firstly, let us assume that the crewman and survivor have fallen for half of a second, and once the cable begins to take the load it requires 0.15 seconds to stop the fall, or decelerate the mass to zero speed. The period of deceleration will vary depending on the length of the cable. It is this rapid deceleration time that causes the shock loads and the rate of deceleration can be calculated as follows:

To put this figure into context, it is the equivalent of 906 kg (1,998.6 lb) of mass, or 3.33 times the original weight of our crewman and survivor. It is this force or load, that the cable must absorb in order to carry the “shock load.”

Note that the deceleration time is critical and will be directly dependent on how much cable is payed out. In the previous example, had the deceleration occurred in 0.1 second the resultant dynamic force applied to the cable would be the equivalent of 1,360kg (2,994lb), or five times the original weight.

The calculations we have provided are relatively simple and valid only for the specific examples discussed. Here we have used simple Newtonian physics to give you an appreciation of the loads involved. The pure engineer will use work and energy relationships with a knowledge of cable elasticity. Results using this method will yield similarly alarming results.

In addition to the effect on the cable and hoist mechanism, an understanding of these calculations will show how dramatically shock loadings can impact on the flyability of the aircraft. It is not difficult to imagine the effect of a brief and almost instantaneous effective weight increase, equivalent to several extra people, applied to the helicopter when maneuvering in sometimes marginal conditions.

Beyond the Cabin
Hopefully, in light of these simple examples, you can appreciate how easily extraordinary loads can develop. Cable management techniques are critically important in ensuring that cable damage, or worse still cable failure, does not occur. In using the term cable management we should extend this beyond the cockpit/cabin to the maintenance arena. Like the rest of an aircraft, the cable is an aeronautical product that requires detailed and regular inspections, coupled with a rigid maintenance regime. In my experience most organizations have got this aspect well under control. However, here are some basic checkpoints to ensure your team is on the game.

Cables require:

• Washing and oiling – extremely important in salt environments
• Regular inspections. Traditionally this has been done visually looking for broken strands, kinks, corrosion etc. The visual method is still important – however equipment that x-rays the cable while washing and oiling it does the best job.
• Hoist inspections and pre-flights must include assessing the unit for smooth running – no binding or restrictions, and ensuring the cable winds correctly on the drum.

It is in the cabin, however, that the “rubber meets the road.” Cable management is a discipline that must become second nature to the winch- and wire-man alike. Ensuring that there is always minimal cable payed out (i.e. minimal slack), will go a long way to reducing the likelihood of a shock loading incident. Winching directly to yachts or small boats can be perilous and should be avoided, particularly in a rough sea state. The opportunity for a shock loading incident whilst conducting winches to a dynamic
vessel provides the opportunity for snag hazards and sudden weight application, if the vessel is to drop away suddenly or the wireman is to slip or fall overboard. The issue is further complicated at night, as you might imagine. Techniques such as Hi-Line and Floating Line access should be used wherever possible to reduce the possibility of a cable snag.

Fast Roping
Some military and para-military operators are, through necessity, attaching the fast rope to the winch hook – but this is not the preferred method. It must be underpinned
by rigorous engineering analysis, although it is unlikely that the manufacturer will agree that it is a good idea. Typically, manufacturers do not endorse abseiling or fast roping from a housed or extended hook. The ropes used in these evolutions will absorb much of the associated loads due to their being able to stretch. The residual loads, however, will be transferred directly to the hook and cable. With very little extended cable, referring back to our discussion so far, all of that load and more will be transferred to the cable. If this is the only option, and fast roping or abseiling must be done for the mission at hand, it is imperative to approach the manufacturer and ensure a thorough engineering analysis has been completed, providing the necessary safety margins to use this configuration.

Clutching the Solution
Hoist systems now coming on to the market are addressing the issue through engineering design. Breeze Eastern, for example, has introduced a Reactive Overload Clutch (ROC) that is designed to recognize a shock loading event and allow the cable to pay out commensurate with the load experienced. The best way to think of this system is that it operates similar to a drag device on a fishing reel.

Shock loading on cables may not result in the cable breaking, but will certainly have an affect on the life of the cable. There is no real way of knowing how much shock load has been applied to a cable during its life, or indeed on any given event. Good SOP is to educate crews on the dynamics of shock loading; how to manage it and to report it to maintenance when it does occur, so that an on-condition inspection can be made. The forces associated with shock loading can be very high and a mismanaged winch evolution, or snag during a rescue, can easily result in cable breakage. In that event, at best you’ve lost the SAR asset and can no longer fulfill the task at hand – at worst somebody was on the cable and the dire consequences of that scenario are obvious to all of us.

Reefdog 13th November 2009 13:36

Hi Ned
Found the above very very very interesting
having come from a winching enviroment and with 38 winches in anger under my belt and countless training winches. i was never ever taught this..
We all know that the cable can take so much but your explanation was enlightning to say the very least..
Enlight of what has happened to the very experienced pilot out of YHID, perhaps this should be taught inline with getting a winch endorsement..
My thoughts go to all involved in the incident,,

Ned are you going to be at the Dubai air show next week,,if so Ill look you up

reef

Liq 14th November 2009 02:34

Funnily enough, even as a non-pilot wannabe, this isn't news to me.

They usually teach all of these concepts at basic rockclimbing/abseiling courses.
The difference between a "static" and "dynamic" line could literally be a matter of life or death, if you fell more than a meter...or at least major injury, as a inflexible static line through a body harness = a rather uncomfortable save.

Great article.

tecpilot 14th November 2009 10:09

Ned,

that is a very good article. My respect to Mr. Smallhorn!
Easy to understand also for non-engineers, but with the needed technical background.

As a pilot, engineer and climber as well i teached a lot of people in such physics. Followed by flight instruction for hoist and shorthaul operations, external load courses, abseiling and fast roping on different types of helos.

Liq,
yes it is allways the same, as i think Newton is still in use :p, but a lot of guys have never heard about such things. And a lot of people do not understand that it can be also important for external load operations. A lot of FTOs do not teach that kind of basics during external load or hoist training.

Shockloading is much more dangerous while using (cheaper) steel products than with fiber ropes (except Dynema, also critical for shockloading)

Last year i visited a operator in the UK, still allways on old chains or steel ropes and wondering about lost loads. They had never heard about the differencies between WLL and the "breaking strength" given by the manucfacturer.

Ned,
i would like to add to Mr. Smallhorns article the fact, that load peaks induced by shockloading can open or break hooks and leading to lost loads also without cable failures.

Some years ago i posted about a deadly logging accident caused by shockloading with load peaks here on PPRuNe.

Gavin Charles 21st October 2010 03:14

Shockloading
 
Great article Ned, have been a Winch operator for 16 years and have seen many a close shave, glad we have an excellent engineer who takes good care of our cables and replaces them soon as they are approaching their limits. I was very impressed with the math, been well aware of shockloading but after seeing the math will again stress to our new staff the importance of load management.

Cheers

Hell Man 21st October 2010 05:17

On another post some place else about lifting I mention the hazards of using inappropriate equipment for line work - specifically the dangers inherent in using chains which a lot of you Kiwis were found doing some time back.

The ability of a chain to manage sudden increases in force (shockloads) is minimal compared to steel rope and one of the many reasons that you shoud never use chains.

I flew a season in PNG, worked with many great Kiwis. There was a free-lancer, wonderful guy called Ray - it was 1989. He goes back to Kiwiland on his tour, flies some work there in a 500 (using a chain) the thing snaps (from a shockload) and the portion of chain above the break rebounded into the 500's disc. Down came Ray, 500 and all .. :( He didn't make it. RIP

Please, if there's anyone out there still using chains for lift work - don't! Put is on your dog or wrap it around your gate but don't put it underneath your helo.

For those who don't understand what shockloads are (maybe school kids reading the forum - yeah rite!) its just rapidly applied force - dat's all!

For the heard-headed Kiwis who can't believe somethin till they see it - go select a bunch of different materials, chains, wire rope, nylon rope or whatever, go hook it up to your favorite vehicle and test-tow your neighbors car. Put granma in the car being towed (coz granma's always slam on the breaks just when the slack is taken up) and watch how the different materials respond to shockloads.

You know how when you tow a car and you some to a stop, the slack builds up, then you accelerate away again (especially if you keep movin) almost always there's a pretty good 'jolt' on the line - well that's a shockload. A chain will wind up smacking the back of your car when it snaps, a nylon line will simply break and may have some recoil depending on how the rope was wound and how heavy it is - doesn't really matter for towing cars. But, steel rope, more often than not, will save your ass when you've got somethin hanging beneath your bird!

HM

SuperF 21st October 2010 11:41

hi guys,

Always knew, or had been told at some point in time about shock loads, what is your opinion on dropping loads? especially close to max all up weight loads, and how do the different helicopters handle it, if there is a difference?

Air shows, etc, always ask if you can come and drop a car, we always refuse, not keen to put the ol girl through that treatment, as we know what a light load release is like, always thought you run the risk of neg-g, mast bump, blade strike on the tail boom, or some other equally exciting force that ends your day, and life, too soon. Anyone done the equations on that?

Also water buckets with multi dump ability, we have them ourselves, can put a fair bump through the helicopter when shutting a 3/4 full bucket to go to the next drop, i guess that is shock loading? should we even be doing it, or should we just go back for another load???

Peter-RB 21st October 2010 12:56

If there is any possibility of a shock load in any lifting proceedure, then it should really be planned out at the initial stages, however when lifting weights that "Could Move" a good idea would be to use either a strop or Roundsling on the object to lift/transport and attach that to the winching wire, so any sudden movement of load or alteration of lifting plane would be absorbed by the Strop/roundsling.

I have used roundslings on coils of steel up to 25tonnes in weight , the coils are not always concentric in shape and the effect of weight on one side of the imaginary centre spindle has in the past sheared lifting cables rated at 50tonnes , further , lifted weight that drops then requires the crane gearboxes to be stripped and crack tested, so I would think a heavy weight suddenly released from a heli would also have a similar effect somewhere in the system!

Peter RB
Vfrpilotpb:eek:

SuperF 23rd October 2010 12:14

I also saw the helicopters dropping the concrete blocks and couldn't figure out why they didn't just place them into the water and release when they hit the ground/water. Relatively easily done if you are watching the load yourself, ask the logging guys they go round in circles every day doing it, and I'm sure they don't drop a log if they can help it...

Have done blocks into water myself, and you would be amassed how much weight comes off the hook when they hit the water, just before you release, if you get really good, you can't even feel it, if you are too early you really know, and depending on the tide, and the size of the block, if you are too late you know about it as well as it takes off in whatever direction the water wants to take it... You then go along for the ride until you release it, which you try to do really fast, or until it hits the bottom..... You don't mess it up after the first time:eek:

tecpilot 4th December 2010 08:09

Helicopter hoist cables -breaking load
 
What are the real breaking loads on the common 4-6mm diameter hoist cables?

For certification they need only a static 3,5 load factor on the to be certified load of mostly 270kg. But have they forgotten "shock loading"?

As example:
Two person should be lifted out from a cliff. Weight all together incl. backpacks, harnesses, helmets, hoist hook = 200kg

The hoist cable is not tight.

Our dummys starting to fall. Fall length only 1m.

Hypothetical there is no damping in the load chain, cause steel ropes have nearly no damping. Ok in reality there is a small one on bodys, harnesses, helicopter, but hypothetical.

Without damping the working force on our 200kg dummys after the full stop 1m-fall is around 19kN. BTW it means 10g on our poor dummys.
On a 2m-fall the working force is crazy 39kN. I bet thats much more than the cables will tolerate.

But in real rescue ops the described case is not impossible.

helisphere 20th December 2010 00:41

I can see the point of not wanting to routinely drop loads but I don't see any serious danger if proper equipment is being used and I certainly don't see the potential for low g as some are suggesting here.

Also remember that the helicopter itself is not rigidly held in space, it moves when forces are applied to it, and when a shock load happens that shock is not just a function of the weight and velocity of the load and the spring constant of the line but there is also the inertia of the helicopter itself which lets the the load decelerate in a longer distance thereby reducing the max force of the shock load.


All times are GMT. The time now is 16:42.


Copyright © 2026 MH Sub I, LLC dba Internet Brands. All rights reserved. Use of this site indicates your consent to the Terms of Use.