PDA

View Full Version : MoD: Major Projects Report 2005


tucumseh
5th Jul 2006, 17:22
MINISTRY OF DEFENCE: MAJOR PROJECTS REPORT 2005

Source: House of Commons Public Accounts Committee

The Major Projects Report 2005 provides information on the time, cost and performance of the Ministry of Defence's (the Department's) 20 largest projects where the main investment decision has been taken; and the 10 largest projects in the Assessment Phase.

For the approved projects, forecast costs were some £700 million lower compared to the previous year. This change was primarily due to reductions in either capability or platform numbers to balance the overall programme. Total forecast costs for these projects now amount to £29 billion, some 10% over budget. In-year timescale slippage increased by 45 months, giving a total delay of 375 months, or an average of some 20 months per project. The Department does, however, expect to meet the majority of its Key User Requirements.


Conclusions and Recommendations

1. The Department has reduced the forecast costs of its top 19 projects by some £700 million. These reductions in forecast costs were not the result of better project management but were cuts needed to bring the Defence Equipment Plan under control. The Department achieved these reductions by cutting the numbers or capability of equipment, and has yet to demonstrate that it can consistently manage individual projects to deliver the planned operational benefits to the Armed Forces to cost and time.

2. Some of the latest capability cuts are short-term expediencies which may result in an erosion of core defence capability or in higher costs throughout the life of individual projects. When deciding how to live within its overstretched budget, the Department should not make short-term cuts without first spelling out the longer-term negative impacts in terms of core capability or poor value for money.

3. The Department's defined levels of capability do not include the quantity of equipment bought. So they can allow quantities to be cut to offset cost overruns, without affecting measured capacity. In defining threshold levels (minimum acceptable capability) and objective levels (full capability desired) for equipment capability on projects coming forward for approval, the Department should reflect quantities as well as performance characteristics.

4. Despite previous assurances that it had restructured many of its older projects, at considerable cost, to address past failures, the Department still attributes much of its historic poor performance to so called "toxic legacy" projects which continue to accumulate considerable time and cost overruns. The Department cannot indefinitely hide behind past deficiencies, while claiming to be taking a proactive approach to addressing the problems. It is time that these projects were put on a firm footing with realistic performance, time and cost estimates against which the Department and industry can be judged.

5. The Department has improved its practice in setting meaningful in-service dates, but still not all future in-service dates represent the delivery of useable capability to the frontline. In defining these dates it needs to incorporate areas such as logistic support and training to enable the Armed Forces to use the equipment effectively.

6. In co-operating with the United States on defence projects, the United Kingdom is the junior partner, which reduces our influence over the project's direction. Conversely, a lack of focused leadership has stymied progress on many European collaborative projects. The Department should routinely analyse co-operative projects to see how far the expected benefits are delivered, so that it can make better informed decisions before committing to future co-operative acquisitions.




Somewhat scathing. I imagine MoD's internal reaction will be the usual "Ignore it. It refers to previous years and we have moved on/improved". Most here will find item 3 unbelievable. It's true.

Severance
5th Jul 2006, 17:47
It appears to be written in an alien tongue:ugh:

What's it all about, besides a lot of excuses couched in management drivel?

Safeware
5th Jul 2006, 18:00
Is Typhoon still excluded from such reporting?

sw

tucumseh
5th Jul 2006, 18:28
SW

I suppose most of the programmes are easy to guess, but I think the sums mentioned are based on latest (re)endorsements rather than the original endorsement; otherwise they would be much worse.



Severance

I guess the summary for those not in MoD is that the PAC have dared to say in public what very many in DPA/DLO have been saying for years – despite it effectively being a disciplinary offence to do so. Most of their criticisms can be overcome by adhering to mandated policy.

The main theme is “The Department achieved these (financial) reductions by cutting the numbers or capability of equipment”. They did not achieve them by being efficient.

Of course, the impression given is that ALL programmes are like this and the justifiable complaint from the many excellent project managers in DPA would be that PAC fails to mention the programmes which are delivered to time, cost and performance. In the words of my old Director in DPA, PMs who do this are “an embarrassment to the Department” because they show what can be achieved – effortlessly. Prat. His bosses agreed with him.

LFFC
5th Jul 2006, 19:37
Committee of Public Accounts: Press Notice No. 50 of Session 2005-06, dated 27 June 2006. (http://www.parliament.uk/parliamentary_committees/committee_of_public_accounts/pac270606_pn50.cfm)

Yes, it's a truly scathing report. :eek:

Mr Edward Leigh MP, Chairman of the Committee of Public Accounts, said today:

“The MOD is still unable consistently to manage individual defence projects so that our servicemen and women have the new equipment they need, when they need it and to cost.

“The Department in 2005 cut the forecast costs of its largest 19 projects by some £700 million. But this is not the good news it seems. Cuts have been achieved mainly by reducing the amount of weaponry on order or by being less demanding about the specifications of the kit. Each project is now expected to be delivered, on average, some 20 months late. And the total forecast cost of the largest projects still stands at £29 billion, compared with the original budgeted figure of £26 billion.

“The MOD is continuing to put some of its poor performance down to a number of ‘toxic legacy’ projects. This hand wringing has gone on far too long. It is now time for the Department finally to get a firm grip on these projects and provide truly realistic performance, time and cost estimates.”



In fact, it's so bad that the MOD couldn't and haven't ignored it. Their "Enabling Acquisition Change" document, released on Monday, identifies many of the major problems and suggests solutions. I really hope that the MOD has the ability to quickly make the changes required! Our front line needs serious support right now!!!

tucumseh
5th Jul 2006, 21:14
LFFC

Agreed, but the majority of the recommendations in "Enabling Acquisition Change" are either (a) mandated policy (b) common sense and used by experienced PMs anyway (c) long standing suggestions which have been rejected by past and current DPA/DLO management or (d) a return to previous policies (some of which were tried and tested and should never have been cancelled).

My suggestions: Identify projects (and their managers) which have been effortlessly delivered to time, cost and performance. Put these people in positions of authority - if only as troubleshooters in the first instance - and learn from them. And for goodness sake sack the fraudsters who condone and practice deliberate waste of public funds and who abrogate their responsibility on an industrial scale.

vecvechookattack
5th Jul 2006, 21:16
Excellent news indeed. At last something is being done about it. We have waited long and hard for a bit of action on this but finally it would appear that there is progress being made.

Toxteth O'Grady
6th Jul 2006, 06:14
Excellent news indeed. At last something is being done about it.

Ahh, but they could have taken it one step further and had a radical overhaul of procurement, such as working closer with industry in integrated project teams using lean processes. They could have had one arm of the organisation looking after procurement and one arm dealing with in-service logistics. It would have been much, much leaner and smarter and it could even have been given a banner headline (ta-dah) "Smart Procurement." If that hadn't quite worked they could then have employed Dilbert as a management consultant to solve all our problems by changing to "Smart Acquisition."

OMFG, it's Groundhog Day!!

It'll never change. The kit we get is only as good as the contract/spec that we write and, just as importantly, the bullishness of the Project Manager in carrying it through to completion. tucumseh hit the nail on the head: this needs quality PMs and there ain't too many around.

Bottom line is that the defence contractors will always want cost overruns to be borne by the customer (aka the taxpayers) rather than by their shareholders/profit margins.

It takes a good contract/spec and hard-nosed Project Managers and Contracts Officers to fight this; the very same people that tucumseh said need to be in positions of authority.

Will that ever happen? Unlikely.

:cool:

TOG