Construction update

The Dart is scheduled to open in the first quarter of 2022

The framework of a new walkway connects the existing passenger footbridge to the first floor entrance of the Dart station (when it is built) via the new footbridge that also passes over the railway tracks.


As can be seen the foundations of the Railtrack funded concourse are now in place.


The framework of a concrete support column can be seen to the left while to the right is a possible lift shaft.


The frontage of the Dart station has been cleared. In the background can be seen the tracks which enters the station on the first floor. The walkway can be seen through the glass wall.


Careful examination shows the new walkway connected to the existing footbridge while the Dart track entrance is to the right of the station.


At Central Station progress seems to have slowed down.


With the station in the foreground, in the background can be seen multi story car park 2 which remains closed. With a few cars still parked on various floors there are no signs of any work being carried out yet. In the past there has been repairs carried out to the fire escapes which showed light flaking and cracking to some of their precast walls