A new double airbridge is being added. This will be operational from July. Some works have commenced on Alpha stands to be able to reconfigure the stands to allow for room on A13 for the new airbridge.
Satellite 3:
The whole satellites gates will be remodelled to match the trial at Gate 43 (In place for about 4 months) This features a slightly changed queuing system designed for Ryanair’s ‘Priority’ and ‘Non-Priority’ boarding process, it also feature perched seating along the queue. No completion or start date for this.
Also new Fixed Electrical Ground Powers Units and Advanced Visual Docking Guidance System with be added to all adjoining stands.
Track-Transit-System TTS:
A re-life project is being looked at to add service life or to replace certain parts of the system, which is nearing 30 years old.