Construction update

Work on Parkway interchange continues with first of two beams being lifted into position where the track will enter the station


The covers are back off the gateway bridge after the sections were welded together. Trusses are being laid either side to support the framework of wood that the concrete trackbed will be poured into. This is going to end up being a mighty weight that will have to be lifted and transported down the hill.


The temporary Taxiway Bravo route is just waiting for its final layer of tarmac. The taxiway sits over the DART tunnel.


Meanwhile just inside the CTA trusses are being put in to support the pouring of the tunnel roof.


MS1 is being clad. The first multi story to be completed is called MS2


At the other end the cores are also being clad but in a lighter shade of grey.